Permit Review Detail
Review Status: Requires Resubmit
Review Details: DEVELOPMENT PACKAGE REVIEW v.1
Permit Number - TD-DEV-0223-00127
Review Name: DEVELOPMENT PACKAGE REVIEW v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
03/15/2023 | Commercial Plumbing | APPROVED | |||
03/08/2023 | NPPO | APPROVED | |||
02/14/2023 | OK to Submit - Zoning | NOT REQUIRED | |||
03/15/2023 | CDRC Post Review | PENDING ASSIGNMENT | |||
03/15/2023 | Site Engineering | REQUIRES RESUBMIT | 1) This Development Package, TD-DEV-0223-00127, Grenier project number 22171, is for distribution way improvements similar to those included in DP22-0255 without the curb cuts, and what appears to be differing pavement profiles and details. DP22-0255, Grenier Job Number 22065, has been submitted and is out for resubmission. This Development package is for lot 56 and includes what appears to be the same segment of Distribution Way. In addition to these, TD-DEV-1222-00077 is a development package (Out for resubmittal), Kimley-Horn project 096648052, for lots 57-59, which appears to continue the planned paving in this package to the west. Please provide a coordination plan for these various Development Packages, and a priority list explaining which elevations, etc. are primary, and anticipated sequencing. 2) In addition to this, please provide an improvements completion plan by the Rita Ranch Commerce Owners Association. Currently, 80% of the lots in this subdivision have been released to date. City of Tucson standards require full completion of all assurable items once the project reaches 75%. Joshua Garcia Engineering Associate Joshua.garcia@tucsonaz.gov |
||
03/08/2023 | Site Landscape | REQUIRES RESUBMIT | See zoning comments. | ||
03/07/2023 | Site Zoning | REQUIRES RESUBMIT | PDSD TRANSMITTAL FROM: PDSD Zoning Review PROJECT: S. Distribution Way Extension Paving & Grading Package (1st Review) TD-DIV-0223-00127 TRANSMITTAL DATE: March 7, 2023 DUE DATE: March 12, 2023 COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 2-06.4.0 CONTENT REQUIREMENTS 1. COMMENT: 2-06.4.3 – Provide the development package case number, TD-DEV-0223-00127, adjacent to the title block on all sheets. 2. COMMENT: 2-06.4.9.H.1 – Some type of barrier will be provided at the temporary end of Distribution Way to prevent vehicles from accessing the unimproved area. If you have any questions about this transmittal, please contact Nicholas Martell at Nicholas.Martell@tucsonaz.gov. RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised paving & grading package |
||
02/03/2023 | CDRC Application Completeness | REVIEW COMPLETED | |||
02/21/2023 | CDRC Review Coordinator | REVIEW COMPLETED | |||
02/22/2023 | Fire New Construction | REVIEW COMPLETED | |||
02/07/2023 | OK to Submit - Engineering | REVIEW COMPLETED | |||
02/06/2023 | OK to Submit - Landscape | REVIEW COMPLETED | |||
03/15/2023 | ROW Engineering Review | REVIEW COMPLETED | No Comments David Stiffey David.Stiffey@tucsonaz.gov |