Permit Number: TD-DEV-0125-00025
Parcel: 13507330G

Address:
7510 E 22ND ST

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE NEW v.2

Permit Number - TD-DEV-0125-00025
Review Name: DEVELOPMENT PACKAGE NEW v.2
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
04/16/2025 Commercial Plumbing Standard APPROVED
04/18/2025 NPPO Standard APPROVED
03/24/2025 Traffic Engineering Review Standard APPROVED Traffic Engineering has no comments on this development.
04/18/2025 CDRC Post Review Express PENDING ASSIGNMENT
03/31/2025 ROW Engineering Review Standard REQUIRES RESUBMIT TD-DEV-0125-00025 • 7510 E 22ND ST • V2

1. In accordance with Section 10-01.3.3 of the Technical Standards Manual, a pedestrian circulation path, as outlined in Section 10-01.4.0, must be established along the full street frontage of the development. This requirement includes bringing the curb access ramp at the southeast corner of 22nd St and Prudence Rd, as well as the existing curb access ramps at the driveway entrances, into compliance. Additionally, the cross slope of the pedestrian circulation path within the driveways must not exceed a 1:48 (2.1%). Revise site plan to reflect the preceding.

If you have any questions, please contact Richard Leigh at Richard Leigh at richard.leigh@tucsonaz.gov
03/28/2025 Site Engineering Standard REQUIRES RESUBMIT 1. See TSMR comments.

Stephen Blood
(520) 837-4958
Stephen.blood@tucsonaz.gov
04/18/2025 Site Landscape Standard REQUIRES RESUBMIT Please reflect any changes that may be required per the Site Zoning and Site Engineer TSMR/PDMR. The landscape plans will be approved once the TSMR/PDMR requirements are met.

Thank you.
Chad Keller, RLA
chad.keller@tucsonaz.gov
04/10/2025 Site Zoning Standard REQUIRES RESUBMIT PDSD TRANSMITTAL

FROM: PDSD Zoning Review

PROJECT: Circle K - 7510 E 22ND ST
Development Package (2nd Review)
TD-DEV-0125-00025

TRANSMITTAL DATE: April 10, 2025

DUE DATE: April 10, 2025

COMMENTS: Resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Section 3.3.3.G.5.c UDC, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is January 30, 2026.

2-06.4.8 - Existing Site Conditions
The following information shall be provided on the plan/plat drawing to indicate the existing conditions on site and within 50 feet of the site. On sites bounded by a street with a width of 50 feet or greater, the existing conditions across the street will be provided.

1. This comment has not be addressed. COMMENT: 2-06.4.8.B – There are several easements shown to be abandoned by separate instrument. These easements will need to be abandoned prior to approval of the DP.

2-06.4.9 - Information on Proposed Development
The following information on the proposed project shall be shown on the drawing or added as notes.

2. This comment was not addressed. The land split number you provided, TD-DIV-0225-00024 is for address 6930 E. Camino Boleadoras not 7510 E. 22nd St. Zoning was not able to find a land split permit associated with this site. COMMENT: 2-06.4.9.E - As it appears that some type of land split/reconfiguration is proposed this split/reconfiguration will need to be processed and approved prior to this DP.

3. This comment was not addressed. COMMENT: 2-06.4.9.R – Clearly demonstrate that the requirements of TSM Section 7-1.4.1.A are met out to 22nd St.

If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov.

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: A revised development package as well as a comment response letter. To resubmit, visit the Tucson Development Center Online at https://tdc-online.tucsonaz.gov/#/home. The instructions for resubmittal can be found at https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/tdc-faq/new-pdfs/revisions-and-resubmittals.pdf.
03/28/2025 TSMR/PDMR - Engineering REQUIRES RESUBMIT 1. ES needs to approve the trash enclosure modification, I have reached out to Andy Vera for approval.
2. See zoning comment for the removal of the required pedestrian circulation path out to 22nd St. With the large row space separating the site from the sidewalk along 22nd St and with heavier foot traffic using 22nd St, it seems to me that it would be safer to provide that path for pedestrians, even through the vehicle use area, rather than not having it and having pedestrians cut through the landscape area and into the vehicle use area looking for the path not knowing they were supposed to go down prudence and then over. Please show the direct pedestrian connectivity to 22nd St.

Stephen Blood
(520) 837-4958
Stephen.blood@tucsonaz.gov
03/28/2025 TSMR/PDMR - Zoning REQUIRES RESUBMIT Due to the excess ROW between the sidewalk on 22nd St and the property line, it would not be appropriate to remove a pedestrian path out to 22nd. Zoning has no issue with modifications to the trash enclosure.
04/07/2025 External Reviewers - Tucson Electric Power (TEP) Standard REVIEW COMPLETED April 4, 2025
WO#T143754
City of Tucson
Planning and Development Services
Attn: CDRC Admin Team
Dear CDRC Admin Team
Subject: Circle K Raze and Rebuild
TD-DEV-0125-00025
Tucson Electric Power Company (TEP) has reviewed and approved the development
plan submitted 2/3/2025. There are existing facilities within the development which are
depicted upon the plan. TEP Facilities will need to be removed or relocated prior to
release of easement, which will be billable. Further, please see attached Book 8493
Page 606 for reference. Any newly installed equipment will require new easements.
Enclosed is a copy of a TEP facilities map showing the approximate location of the
existing facilities. Any relocation costs will be billable to the customer.
To apply for electric service, please call the New Construction department at (520) 918-
8300. Please submit a final set of plans including approved site, electric load, paving
off-site improvements and irrigation plans. If available, include a PDF version of the
plans.
If easements are required, they will be secured by separate instrument. Should you
have any easement questions, please contact our Land Resources Department,
LandReviews@tep.com.
Should you have any technical questions, please contact the area designer,
Martin Rodriguez
(520) 991-5495
mrodriguez@tep.com
Sincerely,
Design Admins
Design Admins