Permit Number: TD-DEV-0124-00012
Parcel: 13303332A

Address:
2205 N WOODS PL

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE NEW v.1

Permit Number - TD-DEV-0124-00012
Review Name: DEVELOPMENT PACKAGE NEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
02/29/2024 Commercial Plumbing APPROVED
02/26/2024 External Reviewers - Pima County Addressing APPROVED Good afternoon,
Pima County Addressing approves TD-DEV-0124-00012. The ADU will be identified as Unit 1 and the main home as Unit 2.
Nicholas Jordan
Site Review Project Manager – Addressing Official
Pima County Development Services Department
201 N Stone AV – 1st Floor
Tucson, AZ 85701
(520) 724-9623
01/31/2024 External Reviewers - Tucson Electric Power (TEP) APPROVED Tucson Electric Power Co., (TEP) has reviewed and has no objection to plat submitted January 25th, 2024. Costs for removing or relocating existing TEP facilities will be billable to the developer.

Please call the New Construction Department at 520-918-8300 to apply for service for new development. Submit a final set of approved plans, including electrical load and offsite improvement plans to determine how TEP will serve this development. If easements are required for new TEP facilities, they will be obtained by separate instrument.


Respectfully,
Tucson Electric Power Co.
Land Resources Department
02/23/2024 NPPO APPROVED
02/23/2024 ROW Engineering Review APPROVED No Comments

David Stiffey

David.Stiffey@tucsonaz.gov
02/23/2024 Site Zoning APPROVED
02/23/2024 Site Landscape NOT REQUIRED
02/29/2024 CDRC Post Review Express PENDING ASSIGNMENT
02/23/2024 Site Engineering REQUIRES RESUBMIT 1. The proposed casita is in a regulatory floodplain and will need to be elevated one foot above the base flood elevation of 2587.30 feet NAVD88. Please also submit for a floodplain use permit with elevation certificate in the TDC Online portal.

For reference: The elevation of the building must be certified by a registered land surveyor at two points during building: first before the pre-slab inspection, when the foundation forms are up, and second when construction is nearly complete, before any final inspections can take place. There will be holds put on the building permits that prevent these inspections until the elevation certificates are submitted to the floodplain use permit in the TDC Online portal.

Lianne Evans
lianne.evans@tucsonaz.gov
01/17/2024 CDRC Application Completeness Express REVIEW COMPLETED
01/25/2024 CDRC Review Coordinator Express REVIEW COMPLETED Review request email sent per Addressing & TEP. CDRC sent FYI email to PAG, USPS, SWG.
01/25/2024 External Reviewers - Pima Association of Governments REVIEW COMPLETED CDRC sent FYI email to PAG, USPS and SWG. No further action is required from customer at this time.
01/25/2024 External Reviewers - Southwest Gas REVIEW COMPLETED CDRC sent FYI email to PAG, USPS and SWG. No further action is required from customer at this time.
01/25/2024 External Reviewers - United States Postal Service (USPS) REVIEW COMPLETED CDRC sent FYI email to PAG, USPS and SWG. No further action is required from customer at this time.
02/16/2024 Fire New Construction REVIEW COMPLETED
01/24/2024 OK to Submit - Engineering Fast REVIEW COMPLETED The site is located in a regulatory floodplain and will require a floodplain use permit before issuance.

Lianne Evans
lianne.evans@tucsonaz.gov
01/19/2024 OK to Submit - Landscape Fast REVIEW COMPLETED
01/24/2024 OK to Submit - Zoning Fast REVIEW COMPLETED 1. Per UDC 6.6.3.C, detached accessory buildings, including accessory dwelling units, are not permitted in the buildable area extending the full width of the lot between the principal building and the front street lot line.

Loran Shamis
Loran.Shamis@tucsonaz.gov