| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 03/25/2024 | Commercial Plumbing | APPROVED | |||
| 03/20/2024 | NPPO | APPROVED | |||
| 03/19/2024 | Site Engineering | APPROVED | |||
| 03/20/2024 | Site Landscape | APPROVED | |||
| 03/25/2024 | CDRC Post Review Express | PENDING ASSIGNMENT | |||
| 03/01/2024 | Fire New Construction | REQUIRES RESUBMIT | -The proposed plan does not meet the 20" minimum for fire department access roads. IFC 503.2.1 john.vincent@tucsonaz.gov 5203495581 |
||
| 03/20/2024 | ROW Engineering Review | REQUIRES RESUBMIT | TD-DEV-0123-00099 7373 E. Valencia Rd. 2nd Review Comments: 1. Key Note No. 18, needs to be noted on the plan as to where this will be installed. 2. 25’ radius header returns must be noted on the plan. 3. Paved entryway. Engineer and appropriate structural section; us City Mix No. 2 This needs to be noted on the plan. 4. The Width of the entrance must be noted on the plan. 5. The “Near Side” existing Sight Visibility Triangle is incorrect. Please correct it to 345’ David Stiffey DTM Project Coordinator David.Stiffey@tucsonaz.gov |
||
| 03/20/2024 | Site Zoning | REQUIRES RESUBMIT | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Nathan Herrera Planner PROJECT: Development Package TD-DEV-0123-00099 TRANSMITTAL DATE: March 20, 2024 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM). 1. 2-06.4.9.H.5 - If utilizing parking area access lanes (PAALs), they shall be designed in accordance with Section 7.4.6, Motor Vehicle Use Area Design Criteria, of the UDC. COMMENT: Per UDC 7.4.6-2, One-way access lane or PAAL serving as a fire lane must be at least 20 feet wide. Show how the above requirement is being met with the proposed entrance configuration. If you have any questions about this transmittal, please contact me at Nathan.Herrera@tucsonaz.gov or at 520-837-4894. RESUBMITTAL OF THE FOLLOWING IS REQUIRED: revised Development Package along with a detailed response letter, which states how all Zoning Review Section comments were addressed. To resubmit visit Tucson Development Center at https://tdc-online.tucsonaz.gov/#/home. Instructions for resubmittal - https://www.tucsonaz.gov/files/sharedassets/public/pdsd/documents/tdc-faq/new-pdfs/revisions-and-resubmittals.pdf. |
||
| 02/12/2024 | CDRC Application Completeness Express | REVIEW COMPLETED | |||
| 02/27/2024 | CDRC Review Coordinator Express | REVIEW COMPLETED | Review request email sent per TEP. | ||
| 03/04/2024 | External Reviewers - Tucson Electric Power (TEP) | REVIEW COMPLETED | Greetings, Tucson Electric Power Co. (TEP) has reviewed and has no objection to the plans submitted on February 27, 2024. There are existing TEP facilities within the boundaries of the plans. Costs for removing or relocating existing TEP facilities will be billable to the developer. Please call the New Construction Department at 520-918-8300 to apply for service for new development. Submit a final set of approved plans, including electrical load and offsite improvement plans, to determine how TEP will serve this development. If easements are required for new TEP facilities, they will be obtained by separate instrument. Respectfully, Tucson Electric Power Co. Land Resources Department |
||
| 02/14/2024 | OK to Submit - Engineering Fast | REVIEW COMPLETED | |||
| 02/27/2024 | OK to Submit - Landscape Fast | REVIEW COMPLETED | |||
| 02/20/2024 | OK to Submit - Zoning Fast | REVIEW COMPLETED |