Permit Number: TC-RES-1224-07492
Parcel: 125151260

Review Status: Requires Resubmit

Review Details: RESIDENTIAL SIMPLE REVIEW v.1

Permit Number - TC-RES-1224-07492
Review Name: RESIDENTIAL SIMPLE REVIEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
12/30/2024 Bldg Permits - Post Review Express PENDING ASSIGNMENT
12/30/2024 Light Residential Building Review (OIP) REQUIRES RESUBMIT Please submit your revised documents and provide a letter with a written response letter addressing each of the comments indicating how the Review comments were resolved. Please note the submittal was incomplete and the plan review was conducted using the information presented. The subsequent review could generate more comments after original comments have been addressed.
1. Note and specify all piping materials. ABS or PVC used in DWV system must be Schedule 40 2018 IRC Table P3002
2. The site sewer (and back-water valve, if applicable) is required to have a green tracer-wire from the building clean-out to the sewer main connection. Blue Stake Requirements:
3. Please amend plans to show the following information.
A. Building sewers smaller than 8 inches shall have cleanouts located at intervals of not more than 100 feet 2018 IRC P3005.2
B. Where a horizontal drainage pipe, a building drain or a building sewer has a change of horizontal direction greater than 45 degrees, a cleanout shall be installed at the change of direction. 2018 IRC P3005.2.4
C. The junction of the building drain and the building sewer shall be served by a cleanout that is located at the junction or within 10 feet of the junction. 2018 IRC P3005.2.3
6. Please show on plans the finish floor elevation and the next upstream manhole cover elevation and provide backwater valve(s) as follows; where the finish floor elevation is less than 12 inches above the elevation of the next upstream manhole cover in the sewer, a backwater valve shall be installed in the building drain or branch of the building drain serving that floor. 2018 IRC P3008.1 as amended
Please contact me if you have any questions about these comments.
Mark Masek
Plans Examiner – Building Safety
Planning and Development Services | City of Tucson
main 520.837.4994
email mark.masek@tucsonaz.gov
12/30/2024 PDSD Application Completeness Express REVIEW COMPLETED