Permit Number: TC-RES-1126-06284
Parcel: 141303420

Review Status: Requires Resubmit

Review Details: RESIDENTIAL SIMPLE REVIEW v.1

Permit Number - TC-RES-1126-06284
Review Name: RESIDENTIAL SIMPLE REVIEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
11/12/2026 Bldg Permits - Post Review Express PENDING ASSIGNMENT
11/12/2026 Light Residential Building Review (OIP) Express REQUIRES RESUBMIT If you have questions regarding this Review, please contact Juan Quintana at juan.quintana@tucsonaz.gov
Provide a comment response letter and address the following comments:

1) Provide load calculations including the EV charger (Standard or Optional are accepted). As of Jan. 1, the City of Tucson has adopted the 2024 I-codes and 2023 NEC. Verify that all calculations adhere to the variables present in the new code. EVSE to be calculated at a minimum of 7.2 kW or nameplate rating, whichever is greater. Conductors and OCPDs are to be sized as continuous loads (80% rule) 220.57

2) Provide a one-line diagram with all equipment to be installed (including CTs or electrical monitoring equipment) as a part of the EV charging system. Show the number of conductors required for this installation and the conduit size to determine conduit fill does not exceed 40%. Include EGC and grounded conductors.

3) Provide Manufacturer Specifications of the EV charger to be used. Include any certifications to ensure that the EVSE is UL listed E3403.3

4) Show the location of the EV charger is protected from vehicular impact, indicate return wall depth or show method that will protect the charger and associated electrical equipment E3404.10, 110.27(B)

5) EV charger must be GFCI-capable, alternatively provide a means of GFCI protection (including GFCI Overcurrent Protection Devices (OCPD)) 625.54
11/10/2026 PDSD Application Completeness Express REVIEW COMPLETED