Permit Review Detail
Review Status: Requires Resubmit
Review Details: RESIDENTIAL SOLAR v.1
Permit Number - TC-RES-0523-05080
Review Name: RESIDENTIAL SOLAR v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
06/01/2023 | Light Residential Building Review (OIP) | APPROVED | |||
06/02/2023 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
06/02/2023 | Site Zoning | REQUIRES RESUBMIT | FROM: PDSD Zoning Review Section PROJECT: TC-RES-0523-05080 436 S. Avenida De Palmas. – RX-1 Shade Structure w/Solar & Roof Mounted Solar (1st Review) TRANSMITTAL DATE: June 2, 2023 COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This site is located in the RX-1 zone (UDC 4.7.6). A single-family residence (SFR) is a permitted use in this zone (Table 4.8-1). See Use-Specific Standards 4.9.7.B.6, .8, & .9. The minimum setback is twenty feet (20) facing each interior property line (Table 6.3-1.A). 1. Required perimeter yard setback to the northwest property line is 20’-0”, proposed perimeter yard setback is 9.4’. Per UDC Article 6.6.2.D An accessory structure that exceeds the allowable height of a wall within a perimeter yard and is detached from a principal structure shall comply with the perimeter yard width standards of the principal structure, except that the accessory structure may be built to a parcel line with the consent of the adjoining or, when separated by an alley, adjacent property owner(s). To secure this neighbor setback waiver the following statement must be provided on the plot plan and be signed and dated by the adjacent property owner(s): My Name is____________________ and I am the owner of the property located at_______________________. I have reviewed the site plan and I have no objection to structure being located or constructed________ feet from the property line as depicted on the site plan. Signature: _____________________________ Date: _________________________________ If you are unable to secure the waiver a Design Development Option (DDO) must be submitted and approved prior to approval of this permit. DDO application and requirements can be found at: https://www.tucsonaz.gov/files/pdsd/forms/DDO_for_Setback_and_Height_UDC_8.11.20.pdf. If you have questions about the DDO application or process please contact Wyatt Berger at Wyatt.Berger@tucsonaz.gov or Georgia Pennington at Georgia.Pennington@tucsonaz.gov. 2. Per UDC Article 6.6.3.E The total gross floor area (gfa) of all accessory structures shall not exceed 50% of the gfa of the principal structure. Accessory structures less than 200 square feet gfa and accessory dwelling units are exempt from this requirement. Provide a calculation that clearly demonstrates that the total gfa of all accessory structures do not exceed the allowed 50%. If the 50% is exceeded a Board of Adjustment for Variance will be required. Board of Adjustment application and requirements can be found at: https://www.tucsonaz.gov/pdsd/zoning-administration-applications. If you have questions about the Board of Adjustment application or process please contact Wyatt Berger at Wyatt.Berger@tucsonaz.gov or Georgia Pennington at Georgia.Pennington@tucsonaz.gov. If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov. |
||
05/11/2023 | PDSD Application Completeness | REVIEW COMPLETED |