Permit Review Detail
Review Status: Requires Resubmit
Review Details: RESIDENTIAL NEW DWELLING v.2
Permit Number - TC-RES-0424-02192
Review Name: RESIDENTIAL NEW DWELLING v.2
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 07/29/2024 | Residential Building | APPROVED | |||
| 08/21/2024 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 08/21/2024 | Site Zoning | REQUIRES RESUBMIT | FROM: PDSD Zoning Review PROJECT: TC-RES-0424-02192 2756 N RICHEY - R-2 Attached Garage/Sleeping Quarters (2nd Review) TRANSMITTAL DATE: August 21, 2024 Resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This site is located in the R-2 zone (UDC 4.7.9). A single-family residence is a permitted use in this zone (Table 4.8-2) subject to Use Specific Standards 4.9.7.B.6, .9 & .10. 1. COMMENT: Provide a dimension from the post supporting the covered deck to the east property line. Per UDC Article 6.4.5.B.2 A vertical structural member(s) (i.e., post, column, dormer wall) supporting a roof extension from the principal structure is considered a wall for applying perimeter yard requirements. Also provide a dimension on the elevations from design grade to the top of beam so that perimeter yard setbacks can be determined. Base on the 17’-4” dimension from finished floor to the bottom of beam plus 8” for the beam and 6” to design grade the required perimeter yard setback from the covered deck to the east property line is 12’-4”, no setback dimension was provided. A Design Development Option (DDO) maybe needed to reduce the required setback. 2. COMMENT: Per UDC Table 6.3-2.A, the required side and rear yard setbacks in the R-2 zone are the greater of 6 feet or 2/3 the height of the building wall. Based on a wall height of 23 feet the required setback from the eastern property line to the proposed building wall is 15 feet 4 inches, the proposed setback is 13’-4”. A Design Development Option (DDO) must be submitted and approved to reduce the required setback. 3. COMMENT: The street perimeter yard setbacks listed are not correct. Review UDC Articles 6.4.5.C.1.a & .b and provide the correct street perimeter yard setbacks. A Design Development Option (DDO) must be submitted and approved to reduce the required setback. DDO application and requirements can be found at: https://www.tucsonaz.gov/Departments/Planning-Development-Services/Planning-Zoning-Applications/Zoning-Administration. If you have questions about the DDO application or process please contact Wyatt Berger at Wyatt.Berger@tucsonaz.gov or Georgia Pennington at Georgia.Pennington@tucsonaz.gov. The Unified Development Code (UDC) can be found at: https://www.tucsonaz.gov/Departments/Planning-Development-Services/Codes/Zoning-Code. If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov. |
||
| 07/24/2024 | PDSD Application Completeness Express | REVIEW COMPLETED |