Permit Review Detail
Review Status: Requires Resubmit
Review Details: RESIDENTIAL NEW DWELLING v.2
Permit Number - TC-RES-0324-01560
Review Name: RESIDENTIAL NEW DWELLING v.2
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 04/24/2024 | Fire New Construction | NOT REQUIRED | |||
| 05/21/2024 | Site Engineering | NOT REQUIRED | |||
| 05/15/2024 | Site Landscape | NOT REQUIRED | |||
| 05/21/2024 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 05/07/2024 | Residential Building | REQUIRES RESUBMIT | Provide a complete construction plan set showing 2018 IRC compliance after DDO approval. Show exterior wood siding, sheathing and wall framing with a 6” clearance above the ground (R317.1 item 5). This may require a concrete stem when the floor is less than 6” above grade. |
||
| 05/20/2024 | Site Zoning | REQUIRES RESUBMIT | ZONING REVIEW TRANSMITTAL FROM: Wyatt Berger Lead Planner PROJECT: TC-RES-0324-01560 2022 East Lee Street – R-1 Garage (2nd Review) TRANSMITTAL DATE: May 20, 2024 Please resubmit revised drawings with a detailed response letter stating how all Zoning Review Section comments were addressed. 1. Zoning acknowledges a Design Development Option (DDO) is in progress to reduce the required side and rear perimeter yards. If the submitted DDO is approved, upload a copy of the DDO decision letter, in addition to the plan set and comment response letter, after the "notice of intent to appeal" has concluded. If you have any questions about this transmittal, contact me at Wyatt.Berger@tucsonaz.gov or at 520-837-4951. |
||
| 04/26/2024 | Zoning Modifications - DDO | REQUIRES RESUBMIT | The DDO application has been accepted for processing. Please allow 4-6 weeks for this process. If the application is approved, please include in your required comment response letter the following information: DDO case number, the request, and condition(s) of approval. If you have questions, please email Mark.Castro@tucsonaz.gov | ||
| 04/24/2024 | PDSD Application Completeness Express | REVIEW COMPLETED |