Permit Review Detail
Review Status: Requires Resubmit
Review Details: RESIDENTIAL SOLAR v.1
Permit Number - TC-RES-0226-00719
Review Name: RESIDENTIAL SOLAR v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 02/17/2026 | Residential Zoning | APPROVED | |||
| 02/24/2026 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 02/13/2026 | Light Residential Building Review (OIP) - Standard | REQUIRES RESUBMIT | If you have questions regarding this Review, please contact Juan Quintana at juan.quintana@tucsonaz.gov 1) Multiple meters are not permitted for distributed generation (DG) installations except as specifically required by TEP. Per TEP ESR-710 (Customer-Owned Renewable Energy Systems), DG systems are allowed only the required utility service meter and, where applicable, a single approved DG production meter. Additional revenue or utility meters for DG generation are not authorized. All PV generation must be metered and shall not be diverted by ESS or other means. 2) The proposed meter socket jumper/bypass may not permitted. TEP ESRB (SR-405, SR-414, SR-452) states that metering enclosures shall not be used as a conduit or raceway for conductors other than the metered phase, neutral, and equipment grounding conductors. This installation is also inconsistent with NEC 110.3(B) (listed equipment must be installed per its listing) and NEC 230.7 (limitations on conductors in service enclosures). Meter sockets are listed to UL 414 for metered service conductors only, and unauthorized jumpers or alternate routing void the listing. Please provide a UL listing for the TESCO Meter Socket Jumper Cover. Include written authorization from TEP approving its use in this DG configuration. In the absence of such authorization, the extra meter socket shall be removed. If TEP does approve its retention for a non-metered purpose, the meter socket cover shall be permanently secured (non-removable without destruction) to prevent the enclosure from being used as a meter socket in the future. Documentation from TEP and details of the permanent cover method shall be included on resubmission of this plan set. |
||
| 02/24/2026 | Residential Engineering | REQUIRES RESUBMIT | Permit: TC-RES-0226-00719 Location: 2141 S PALM SPRINGS DR Review Date: 2/24/2026 A Comment Response letter is required. Please address all reviewer’s comments in a separate document with all required documents for resubmittal. Residential Engineering Comments: 1. Unable to approve without an approved and issued floodplain use (FPU) permit. TE-FPU-0226-00037 is in “Needs Resubmittal” status, and files will need to be uploaded on TDC-Online to calculate substantial improvement. 2. Resubmit to the FPU permit (TE-FPU-0226-00037) an itemized cost estimate of materials and labor for the installation of new PV system and battery. A lease agreement will NOT be accepted. 3. Upload required documents to both permits on TDC-Online (a revised site plan, comment response letter, and itemized cost estimate). TE-FPU-0226-00037 TC-RES-0226-00719 If you have any questions or concerns, please contact Dylan Molina. Dylan.Molina@tucsonaz.gov |
||
| 02/10/2026 | PDSD Application Completeness Express | REVIEW COMPLETED |