Review Status: Requires Resubmit
Review Details: RESIDENTIAL NEW DWELLING v.1
Permit Number - TC-RES-0123-01916
Review Name: RESIDENTIAL NEW DWELLING v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 02/06/2023 | Site Engineering | NOT REQUIRED | |||
| 02/23/2023 | Site Landscape | NOT REQUIRED | |||
| 02/24/2023 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 02/22/2023 | Residential Building | REQUIRES RESUBMIT | TC-RES-0123-01916 PLAN REVIEW COMMENTS Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. For facilitating a shorter back check time, please provide updated plans and calculations with a written response to each of the notated items indicating action taken. Do not cloud the changes made for comment updates; revisions are processed if changes occur after the permit is issued. SCOPE OF REVIEW: The scope of this plan review covers architectural, plumbing, mechanical, energy conservation and electrical. All code references are to the 2018 International Residential Code and 2018 International Energy Conservation Code. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions and concerns before permit approval. GENERAL REQUIREMENTS: Provide a complete construction plan set with all support documents placed in separate files. The City of Tucson adopted the 2018 IRC with amendments on 1/1/2019. Show the current code reference on the plans. GENERAL COMMENTS : 1. A dwelling unit (living space with kitchen) providing complete independent living facilities requires compliance with design ordinances for handicap, solar water, photo-voltaic, gray water and EV charging preparations. Design Ordinances adopted by the City of Tucson. 2. Show compliance with the Inclusive Home Design Ordinance adopted by the City of Tucson Ordinance #10463 on 10/16/2007. Notate accessible route, minimum door width, changes in floor elevation, door hardware, electrical outlet reach range, grab bar reinforcement, etc. 3. All SFR and Duplex plans submitted after March 1, 2009, require a solar water system, or future installation preparation City of Tucson Ordinance #10549 with one of the following provisions: ½”control conduit and two ¾” copper piping for water with rooftop termination; straight 3” capped sleeve; or an accessible attic (clear path 30” wide x 30” high) over the water heater. Show appropriate notation. 4. All SFR and Duplex plans submitted after July 1, 2009 require a solar photo-voltaic system, or future installation preparation City of Tucson Ordinance #10549 . a. Show a minimum 300 SF clear solar-ready zone on a roof or framing plan, T103.3. Model plans should show four typical south facing roof surfaces. b. Label a double breaker space for future Photo Voltaic on the panel schedule opposite end from the main/supply side, T103.9. Update breaker space to the last panel space. 5. All construction drawings submitted after June 1, 2010, for one- or two-family dwellings must provide gray water utilization or preparation, Ordinance #10579/11089 revised July 9, 2013. The ordinance revision now requires a gray drain line discharge from one fixture for a one story dwelling. Additional gray fixture drains are optional. Show a second clothes washer standpipe plumbed to an exterior wall above grade when feasible, or a bathing fixture drain looped 3’ beyond an exterior wall below grade before connection to the building drain. Use the appropriate detail at https://www.tucsonaz.gov/pdsd/water-energy-conservation 6. Show compliance with the Electric Vehicle Supply Equipment Ordinance adopted by the City of Tucson Ordinance #11844 on 6/22/2021. Include a 40 ampere 240 volt dedicated branch circuit with a NEMA 14-50R receptacle for charging an electric vehicle at a proposed parking space or show the distance from transit or a bike boulevard as not greater than a quarter-mile. SITE PLAN: 1. Update the electric and water lines from meter to building, R106.1.1. Show all utility point of connections without dependance on another dwelling. TEP may require the service panel for the property at the closest building to the service transformer with an underground feeder from a dual meter to the more distant dwelling. 2. Show a street address for each dwelling on the site plan, R319. PLANS: 1. Show a maximum ½” floor elevation changes at a notated accessible route entrance on the floor plan, R106.1.1. Include the threshold condition at the vehicle doorway or an exterior hinged door when the garage is used for the accessible route. 2. Provide manufacturer’s calculations and data for pre-engineered trusses dated and wet-sealed by an engineer who is registered in Arizona, or notate the requirement for deferred submittal, R106.1. SECTIONS - DETAILS: 1. Clarify the placement of ceiling/roof insulation for determining the need for attic ventilation or need for providing air-impermeable rigid insulation at the roof, R806. 2. An unvented roof assembly requires an air-impermeable rigid insulation material with a minimum R-5 value applied correctly to either side of the roof sheathing, R806.5. Show a roof design with insulation types and minimum thickness for meeting the condensation control requirement and the minimum total insulation value of R-38. PLUMBING PLANS: 1. Tucson Water Department limits flow rates for each water meter size in compliance with P2903.7. Show an appropriate yard pipe bypassing the existing dwelling and the water meter size. MECHANICAL PLANS: 1. Provide (an HVAC system with fresh air intake) whole-house mechanical ventilation, or controlled exhaust with a calculated airflow rate, R303.4; N1103.6 & M1505.4. Show the system and appropriate flow rate setting on the plans. A two or three bedroom dwelling of 1501 – 3000 SF requires a 60 CFM continuous setting. 2. Provide demand calculations in accordance with Manual J/S/D standards, M1401.3, M1601.1. Systems shall be sized in accordance with Manual S based on building loads calculated in accordance with Manual J and duct systems sized in accordance with Manual D. Notate if the mechanical plans if system calculations will be provided by deferred submittal. ELECTRICAL PLANS: 1. TEP may require the service panel for the property at the closest building to the service transformer. A service line change or a new meter location must be coordinated with TEP for approval. Show an underground feeder from a metered service panel to the more distant dwelling. 2. Update the Riser Diagram for the close dwelling and the feeder size to the detached dwelling panel, NEC 225.30 and E3403. Show a Riser Diagram providing service disconnect of either dwelling without service disruption of the other dwelling. 3. Provide the Electric Vehicle Supply Equipment 40 ampere 240 volt dedicated branch circuit with a NEMA 14-50R receptacle and label the circuit “EV Ready” and locate the receptacle at a parking area, N1104.2.1. Include the Electric Vehicle load entry (typically 7680 watts) in the electrical load calculations (continuous demand) like the HVAC entry, N1104.2.2. OUTDOOR LIGHTING CODE 1. Show the proposed fixture as full cut-off FCO style or provide an Outdoor Lighting Calculation including all exterior fixtures on the property for determining exterior lighting limits. INTERNATIONAL ENERGY CONSERVATION CODE: 1. Energy Certificate: (Mandatory) place near the indoor furnace or in utility room, N1101.14. Add notation to plans. Please contact the plans reviewer if you have any questions: Ken Van Karsen (520) 837-4912 PDSD-Residential@tucsonaz.gov City of Tucson Residential Plan Review Submit a corrected plan set at https://www.tucsonaz.gov/pdsd |
||
| 02/22/2023 | Site Zoning | REQUIRES RESUBMIT | ZONING REVIEW TRANSMITTAL FROM: PDSD Zoning Review PROJECT: TC-RES-0123-01916 5826 S Park Ave. - R-2 New SFR (1st Review) TRANSMITTAL: February 22, 2023 Provided a detail comment response letter with your submittal that clearly shows how you have addressed all comments with your next submittal. This site is located in the R-2 zone (UDC 4.7.9). A single-family residence (SFR) is a permitted use in this zone (Table 4.8-2). See Use-Specific Standards 4.9.7.B.6, .9, & .10. 1. Clearly show the proposed SFR on the plan. Zoning cannot tell where the structure starts and stops. There is nothing that clearly looks like the floor plan provided. 2. The 3’-4” setback shown along the south parcel line does not appear to be from the south parcel line but from some other line on the plan. 3. It appears you are proposing to add parcel 140-23-069E to parcel 140-23-069B. Zoning was not able to find approved documents for this land split, provide copies of the approved documentation for this split. Parcel 140-23-069E will need to be combined with 140-23-069B prior to approve of this plan. 4. There is a outstanding demo permit, T21BU00237, for the “EXISTING STRUCTURE” shown on this plan. If the proposal is to demo this structure remove the structure and final the demo permit. If this structure is to remain provide a full floor plan for this structure so that vehicle parking requirements can be verified. 5. Provide property dimensions for all property lines on the plot plan. 6. Perimeter yard setbacks are based on a measurement from design grade to the highest point of the exterior wall UDC Article 6.4.5.B & Figure 6.4.5-A. Provide the correct wall height dimensions on the plan. Until the correct dimension and comment 1 has been addressed Zoning cannot provide comments for the DDO. If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov |
||
| 02/24/2023 | Zoning Modifications - DDO | REQUIRES RESUBMIT | ZONING REVIEW TRANSMITTAL FROM: Georgia Pennington, Planner PROJECT: TC-RES-0123-01916 5826 S Park Ave. - R-2 New SFR (1st Review) TRANSMITTAL: February 24, 2023 1. Address all Zoning Review comments prior to DDO submission. The DDO application and requirements can be found at: https://www.tucsonaz.gov/files/pdsd/forms/2019_DDO_for_Setback_and_Height_UDC.pdf. If you have any questions about this transmittal, please contact Georgia.Pennington@tucsonaz.gov |
||
| 02/03/2023 | PDSD Application Completeness Express | REVIEW COMPLETED |