Review Status: Requires Resubmit
Review Details: SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2
Permit Number - TC-MDP-1223-01878
Review Name: SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/03/2024 | Residential Building | APPROVED | |||
| 01/04/2024 | Site Engineering | APPROVED | |||
| 01/04/2024 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 12/26/2023 | Site Zoning | REQUIRES RESUBMIT | FROM: Paul Camarena PDSD Zoning Review Section PROJECT: TC-MDP-1223-01878 236 E 25TH ST Zoning R-2 SFR TRANSMITTAL DATE:December 26, 2023 COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1.COMMENT: The minimum setback is the greater of six (6) feet, or two-thirds (2/3) the height of the structure’s wall facing each interior property line (Table 6.3-2.A). Based on a wall height of 9’-6” the required perimeter yard setback from the proposed SFR to the west property line is 6’-4”, proposed setback is 6’-0”. A Design Development Option (DDO) must be submitted and approved to reduce the required setback, DDO application and requirements can be found at: https://www.tucsonaz.gov/files/sharedassets/public/pdsd/documents/planning-amp-zoning/2019_ddo_for_setback_and_height_udc.pdf . The completed application shall be submitted as a PDF under assigned permit number. If you have questions about the DDO application or process please contact Wyatt Berger at wyatt.berger@tucsonaz.gov or Georgia Pennington at georgia.pennington@tucsonaz.gov If you have any questions about this transmittal, Contact Paul Camarena at (520)837-4986 or by email Paul.Camarena@tucsonaz.gov |
||
| 12/27/2023 | Fire New Construction | REVIEW COMPLETED | |||
| 12/21/2023 | PDSD Application Completeness Express | REVIEW COMPLETED | |||
| 12/26/2023 | ROW Engineering Review | REVIEW COMPLETED | No new construction is proposed in Right-of-Way. |