Permit Review Detail
Review Status: Requires Resubmit
Review Details: BUILDING DEFERRED SUBMITTAL REVIEW v.1
Permit Number - TC-MDP-0623-01138
Review Name: BUILDING DEFERRED SUBMITTAL REVIEW v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 03/11/2024 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 03/11/2024 | Concrete Installation Inspection (Deferred Submittal) Express | REQUIRES RESUBMIT | Post Tension Concrete specification strength within structural drawings is 3,000 psi, four locations are below 3,000 psi (as low as 2,750 psi). Please have Project Structural Engineer review and obtain his recommendation (should he/she decides to approve this report, a seal/signature/date will be required on the Hammer Test result report along with his statement for accepting the test result). | ||
| 03/08/2024 | PDSD Application Completeness Express | REVIEW COMPLETED | |||
| 03/11/2024 | Post-Installed Anchor Inspection (Deferred Submittal) Express | REVIEW COMPLETED | |||
| 03/11/2024 | Post-Tension Inspection (Deferred Submittal) Express | REVIEW COMPLETED | |||
| 03/11/2024 | Site Prep Inspection (Deferred Submittal) Express | REVIEW COMPLETED | SOIL COMPACTION |