Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: TC-MDP-0424-00526
Parcel: 141460600

Address:
9653 E HARKES DR

Review Status: Requires Resubmit

Review Details: BUILDING DEFERRED SUBMITTAL REVIEW v.1

Permit Number - TC-MDP-0424-00526
Review Name: BUILDING DEFERRED SUBMITTAL REVIEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
02/25/2025 Truss Design (Deferred Submittal) Express NOT REQUIRED Truss design review already performed (TC-MDP-1222-00121)
02/26/2025 Bldg Permits - Post Review Express PENDING ASSIGNMENT
02/25/2025 Site Prep Inspection (Deferred Submittal) Express REQUIRES RESUBMIT ACTIVITY NO. TC-MDP-0424-00526
ADDRESS/PARCEL: (9653 E HARKES DR TUCSON, AZ 85747)
Submit your revised drawings along with a detailed response letter, which states how all Building Review Section comments were addressed. The submitted documents were incomplete and a thorough plan review could not be performed. Please be aware, new comments may arise with the next review. Review will not proceed without the response letter.
COMMENTS:
1. Please submit the soils testing field report
2. Instead of crossing out the post installed (epoxy) anchors in Part B, please state the post installed (epoxy) anchors were not utilized for this project in Part C.
02/25/2025 Special Inspection Certificate Review (Deferred Submittal) Express REQUIRES RESUBMIT ACTIVITY NO. TC-MDP-0424-00526
ADDRESS/PARCEL: (9653 E HARKES DR TUCSON, AZ 85747)
Submit your revised drawings along with a detailed response letter, which states how all Building Review Section comments were addressed. The submitted documents were incomplete and a thorough plan review could not be performed. Please be aware, new comments may arise with the next review. Review will not proceed without the response letter.
COMMENTS:
1. Please submit the soils testing field report
2. Instead of crossing out the post installed (epoxy) anchors in Part B, please state the post installed (epoxy) anchors were not utilized for this project in Part C.
02/25/2025 Concrete Installation Inspection (Deferred Submittal) Express REVIEW COMPLETED
02/21/2025 PDSD Application Completeness Express REVIEW COMPLETED
02/26/2025 Pima County Wastewater (Deferred Submittal) Express REVIEW COMPLETED
02/25/2025 Post-Tension Inspection (Deferred Submittal) Express REVIEW COMPLETED