Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
12/26/2023 | Site Zoning | APPROVED | |||
12/26/2023 | Fire New Construction | NOT REQUIRED | |||
01/04/2024 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
01/03/2024 | Commercial Electrical | REQUIRES RESUBMIT | Please address the electrical plan review comments and provide a written response. 1. The marked up plans submitted have expired registrant seals. Please update the registrant seals on the plans and resubmit. Ref; 2018 IBC section 107.1, 2017 NEC. |
||
01/04/2024 | Commercial Structural | REQUIRES RESUBMIT | Submit your revised drawings along with a detailed response letter, which states how all Building Review Section comments were addressed. 1. The structural Engineer Structural Assessment Report recommendation is: "Remove and replace all purlins in the bays adjacent to the girder frame that is recommended to be replaced. The existing purlins should not be reused for this solar canopy. 2. The Solon memo on their proposed repair scope does not reflect the above structural engineer recommendation. Solon is proposing to reuse and re-install purlins. 3. Please correct and reflect the structural engineer recommendation in both letter and drawings. 4. Please resubmit. |
||
01/04/2024 | Site Engineering | REQUIRES RESUBMIT | This project is within a regulated floodplain and requires a Floodplain Use Permit (FUP.) Please start a new FUP at our permit application web page: https://tdc-online.tucsonaz.gov/#/home NOTE: A floodplain use permit is required for work in the floodplain. No cost estimates or elevation certificates are required. Instructions: 1. Navigate into the current project in the “My Work” tab. Within the permit, navigate to the “Sub-Records” tab and click “Apply” on the Floodplain Use Permit Sub-Record 2. Locations -> Confirm the location is accurate to the project. Click “Next” 3. Type -> Fill in the “Square Feet” and “Valuation” boxes with the project area and a contractor-provided cost estimate (See note above: for new structures, input 0). Click “Next” 4. Contacts -> Confirm contacts and add any additional contacts if applicable. Click “Next” 5. More Info -> This will be filled in by the engineer assigned to your case, Click “Next” 6. Attachments -> Please attach the project plan, supporting documentation for the cost estimate (if applicable), and a drainage/hydrology report (if applicable). Click “Next” 7. Signature -> Read the statement and type your name. Sign your name below (You may Enable Type Signature to have the software sign for you.) Click “Next” 8. Review and Submit -> Review all information to ensure accuracy. Click “Submit” Contact Lianne Evans at lianne.evans@tucsonaz.gov or Stephen Blood at Stephen.Blood@tucsonaz.gov if you have any questions about the FUP. |
||
12/22/2023 | PDSD Application Completeness | REVIEW COMPLETED |