Permit Number: TC-COM-1126-01823
Parcel: 13323164A

Review Status: In Review

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-1126-01823
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: In Review
Review Date Reviewer's Name Type of Review Description Status Comments
11/27/2026 Outdoor Lighting Standard NOT REQUIRED No modifications to the outdoor lighting.
N/A Commercial Building Standard PENDING ASSIGNMENT
N/A Commercial Electrical Standard PENDING ASSIGNMENT
N/A Commercial Mechanical Standard PENDING ASSIGNMENT
N/A Commercial Plumbing Standard PENDING ASSIGNMENT
N/A Commercial Post Review Express PENDING ASSIGNMENT
N/A Site Zoning Standard PENDING ASSIGNMENT
N/A Water - PDSD Standard PENDING ASSIGNMENT
11/25/2026 Site Engineering Standard REQUIRES RESUBMIT Permit Activity Number TC-COM-1126-01823 (1st Review)
Project: Installation of 4 EV charging stations and their associated electrical equipment within the existing Walmart parking lot.
Location: 7150 E SPEEDWAY BL
Review Date: 11/25/2026
Reviewer: John Mounsey – Engineering Associate
Reviewer Contact Information: john.mounsey@tucsonaz.gov

Site Engineering comments are as follows:
1. Development Package Required: The proposed EV Chargers at this commercial site requires the submittal of a Development Package (site plan) in accordance with UDC §7.4.3.E. Per UDC §3.3.3.G.2.c, a Development Package (DP) meeting the requirements of the Checklist for Minor Changes to Commercial/Industrial Sites must be submitted and approved. The Development Package is a separate submittal from the building plans and must be processed independently.
2. Site Engineering Review: Site Engineering is unable to fully review and approve permit TC-COM-1126-01823 until the associated Development Package has been reviewed and approved by all applicable reviewers.
11/18/2026 Fire New Construction Standard REVIEW COMPLETED
11/13/2026 PDSD Application Completeness Express REVIEW COMPLETED