Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-1122-00149
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 02/03/2023 | Commercial Building | APPROVED | |||
| 12/12/2022 | Site Zoning | APPROVED | |||
| 01/03/2023 | Site Engineering | NOT REQUIRED | |||
| 02/06/2023 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 02/06/2023 | Commercial Electrical | REQUIRES RESUBMIT | Electric storage (50) gal type water heaters are considered a continuous load per NEC 422.13. See water heater specifications on plan sheet ‘P2’. The WH is rated at 28.8 amps x 125% = 36 amps, therefore requiring a 40 OCPD and # 8AWG Cu feeder conductors #10 equipment ground. Please revise this for the electrical panel schedule and water heater circuit, and load calculations. Ref; 2018 IBC 107.2, 2017 NEC |
||
| 02/06/2023 | Commercial Plumbing | REQUIRES RESUBMIT | The water calculations appear to note the installation of a new reduced pressure backflow prevention assembly but the size is unknown (X” RPBP). Clarify what is being installed. Reference: Section 107.2.1, IBC 2018. |
||
| 01/04/2023 | Fire New Construction | REVIEW COMPLETED | |||
| 12/08/2022 | PDSD Application Completeness Express | REVIEW COMPLETED |