Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
03/13/2023 | External Reviewers - SAFEBuilt | APPROVED | Activity Number: TC-COM-1122-00082 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: Conditionally Approved 1. Drawings marked "good for construction" needs to be stamped with building permit approval, submitted documents are marked "not for construction". 2. Structural engineer needs to ensure before placement of footings for the new canopy that the new footing base is not encroaching into the load transfer area of the footings base of existing foundations. 3. Even though the design is based on 103 mph wind speed which is less than the design wind speed of 105 mph, design is acceptable as enough demand capacity ratio is available structurally and hence a revision to the structural design is not considered deemed necessary. 4. Erection drawings for the canopy complete with connection details have not been provided at this review stage, their submission can be considered a Deferred submittal and those details can be provided later for review and approval. BUILDING REVIEW COMMENTS: Approved MECHANICAL REVIEW COMMENTS: Conditionally Approved Approved/subject to field approval ELECTRICAL REVIEW COMMENTS Approved PLUMBING REVIEW COMMENTS: Conditionally Approved Ok Subject to field inspections If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov |
||
03/24/2023 | Site Engineering | APPROVED | |||
03/24/2023 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
03/24/2023 | Site Zoning | REQUIRES RESUBMIT | FROM: Iman Monshizadeh / PDSD Zoning Review Section PROJECT: TC-COM-1122-00082 / Canopy Addition Plot Plan Review (1st Revision) 775 W Silverlake Rd / I-1 Zone TRANSMITTAL DATE: 3/21/2023 Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1.COMMENT: The total canopy floor area shown on the plans are greater than the area shown on the development package TD-DEV-1122-00023 (22,906 sf). Revise the plans to show floor area and height that is consistent with the development package. For questions regarding Zoning comments, please contact me at: Iman.Monshizadeh@tucsonaz.gov |
||
03/02/2023 | PDSD Application Completeness | REVIEW COMPLETED |