Permit Review Detail
Review Status: Requires Resubmit
Review Details: BUILDING DEFERRED SUBMITTAL REVIEW v.2
Permit Number - TC-COM-1122-00074
Review Name: BUILDING DEFERRED SUBMITTAL REVIEW v.2
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 05/30/2024 | Water Sterilization Report (Deferred Submittal) Express | APPROVED | |||
| 05/30/2024 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 05/30/2024 | Air Balancing/Commissioning Report (Deferred Submittal) Express | REQUIRES RESUBMIT | The mechanical plan provided to the balancing contractor was different from what was installed. Provide a review of the air balance report by the responsible engineer to verify that the installation met his design intent. Reference: Sections 107.3.4 and 107.4, IBC 2018. | ||
| 05/29/2024 | PDSD Application Completeness Express | REVIEW COMPLETED |