Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-1122-00070
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/30/2023 | Commercial Structural | APPROVED | |||
| 11/30/2022 | Commercial Electrical | NOT REQUIRED | |||
| 01/30/2023 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 12/09/2022 | Site Engineering | REQUIRES RESUBMIT | Combo permits cannot be approved until their associated development package is approved. This permit will not be approved until DP22-0188 is approved. | ||
| 11/23/2022 | Site Zoning | REQUIRES RESUBMIT | FROM: PDSD Zoning Review Section PROJECT: TC-COM-1122-00070 – DP22-0188 Cottonwood Substation Screen Wall (1st Review) 6690 S Alvernon Wy / I-1 TRANSMITTAL DATE: November 23, 2022 COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. COMMENT: Zoning has reviewed the screen wall plans for compliance with the associated Development Package DP22-0188. Zoning cannot approve the screen wall plans until the DP is approved. If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov. |
||
| 12/04/2022 | Fire New Construction | REVIEW COMPLETED | |||
| 11/21/2022 | PDSD Application Completeness Express | REVIEW COMPLETED |