Permit Number: TC-COM-1025-01891
Parcel: 11305054B

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-1025-01891
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
11/05/2025 Commercial Building Standard APPROVED
10/27/2025 Commercial Electrical Standard APPROVED
11/04/2025 Commercial Mechanical Standard NOT REQUIRED
11/04/2025 Commercial Plumbing Standard NOT REQUIRED
10/27/2025 Outdoor Lighting Standard NOT REQUIRED No modifications to the outdoor lighting,
11/04/2025 Water - PDSD Standard NOT REQUIRED
11/05/2025 Bldg Permits - Post Review Express PENDING ASSIGNMENT
10/31/2025 Site Engineering Standard REQUIRES RESUBMIT Permit: TC-COM-1025-01891
Location: 3550 N CAMPBELL AV
Review Date: 10/31/2025
Site Engineering Comments:
1. Site Engineering is unable to approve permit TC-COM-1025-01891 until the associated Development Package TD-DEV-1025-00260 is reviewed and approved by all reviewers.
If you have any questions or concerns, please contact
Marco Contreras
Marco.contreras@tucsonaz.gov
11/05/2025 Site Zoning Standard REQUIRES RESUBMIT PDSD TRANSMITTAL

FROM:
Bobby Parsons
Zoning Section Review

PROJECT:
TC-COM-1025-01891
3550 N. Campbell Ave. Tucson, AZ 85719
Replacement of existing underground storage tanks (1st Review)

TRANSMITTAL DATE: 11/5/2025

DUE DATE: 11/4/2025

This site is located in the C-1 zone (UDC 4.7.20). General Merchandise Sales is an allowed use in this zone subject to Use Specific Standards 4.9.9.B.3 and 4.9.13.O.

Comments: Please resubmit revised drawings along with a detailed response letter which states how all Zoning Review Section comments were addressed.

1. Comment: The associated Development Package (DP) TD-DEV-1025-00260 has not completed a full review cycle. While the building permit plans appear to match the DP, Site Zoning is unable to approve this permit until the DP has been reviewed and approved by all reviewers.
2. Comment: Additional comments may be forthcoming depending on responses to zoning comments and plans submitted.

If you have any questions about this transmittal, please contact Bobby Parsons at Robert.Parsons@tucsonaz.gov.
10/31/2025 Fire New Construction Standard REVIEW COMPLETED
10/14/2025 PDSD Application Completeness Express REVIEW COMPLETED