Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-1025-01838
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 10/31/2025 | Commercial Building Standard | APPROVED | APPROVED UNDER MASTER SET LOCATED AT: TC-COM-0725-01397 | ||
| 10/14/2025 | Commercial Electrical Standard | APPROVED | |||
| 10/14/2025 | Water - PDSD Standard | NOT REQUIRED | NOT REQUIRED ON MASTER PERMIT TC-COM-0725-01397 | ||
| 10/31/2025 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 10/09/2025 | Fire New Construction Standard | PENDING ASSIGNMENT | REVIEW COMPLETE ON MASTER PERMIT TC-COM-0725-01397 | ||
| 10/09/2025 | Outdoor Lighting Standard | PENDING ASSIGNMENT | APPROVED ON MASTER PERMIT TC-COM-0725-01397 | ||
| 10/09/2025 | Site Engineering Standard | PENDING ASSIGNMENT | NOT REQUIRED ON MASTER PERMIT TC-COM-0725-01397 | ||
| 10/09/2025 | Site Zoning Standard | PENDING ASSIGNMENT | APPROVED ON MASTER PERMIT TC-COM-0725-01397 | ||
| 10/14/2025 | Commercial Mechanical Standard | REQUIRES RESUBMIT | 1. Provide heating/cooling load calculations to justify the capacity of the unit being installed and provide controls that comply with Sections R403.1 and R503.1.2, IECC 2018. [Second comment: Comment not addressed.] [Initial comment: Replacement of AC units will require heating/cooling load calculations to justify the capacities of the units being installed (Sections R403.7, IECC 2018). The units themselves will also have to comply with Sections R403.1 and R503.1.2, IECC 2018 for controls. The replacement units shall have an efficiency rating that is greater than or equal to the minimum required by the Department of Energy requirements that went into effect on January 1, 2023, for the Southwest part of the country.] 2. State the size and termination point of the dryer exhaust. Reference: Section 504, IMC 2018. 3. Provide the type of combustion/relief openings (i.e. one opening or two openings) and the opening dimensions. Reference: Section 304.1, IFGC 2018. |
||
| 10/14/2025 | Commercial Plumbing Standard | REQUIRES RESUBMIT | 1. Provide a description of the proposed replacement water heater, e.g., manufacturer, model, capacity, and gas input. [Second comment: Comment not addressed.] [Initial comment: The description of work for this activity is to replace a water heater. If it is a like-for-like replacement, submit documents that describe the proposed water heater (e.g., Manufacturer specifications). Reference: Section 107.2.1, IBC 2018.] 2. If the gas inputs for the replacement water heater and furnace are not less than or equal to the gas inputs of the appliances being replaced, provide a schematic diagram of the natural gas distribution piping, including the size, material, and developed lengths of the pipes. Reference: Sections 401.3 and 401.8, IFGC 2018. |
||
| 10/09/2025 | PDSD Application Completeness Express | REVIEW COMPLETED |