Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: TC-COM-1024-01945
Parcel: 10511061P

Review Status: In Review

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-1024-01945
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: In Review
Review Date Reviewer's Name Type of Review Description Status Comments
10/29/2024 Commercial Electrical APPROVED Structural(S) Reviewer
Madeline Nelson
mnelson@safebuilt.com
Denied
Reason:
Date Completed : 10/24/2024 11:17:55 PM
1. GENERAL - UPDATES: For project updates, please submit sheets with all changes clearly marked in revision clouds. Please provide a written response to each comment; updates without a clear response to all comments may not be
reviewed. If you have any questions regarding the comments, you may contact me directly. Updates may result in additional comments.
2. GENERAL - FIRM REGISTRATION: Per the Arizona Revised Statutes, Chapter 32, Rule 141, a firm shall not engage in the practice of any board-regulated profession or occupation unless the firm is registered with the board”. Please
ensure that Hohbach-Lewin, Inc has been properly registered with the State of Arizona under this provision. Refer to the Arizona State Board of Technical Registration (https://btr.az.gov/public/registered-firm-branch-search) for more
information.
3. S100 - WIND DESIGN CRITERIA: Section 1603.1.4 of the 2018 International Building Code lists the wind design criteria that must be provided on the construction documents. Please revise the structural general notes to include the
following:
i. Basic design wind speed, V, expressed in miles per hour
ii. Wind Exposure
iii. Design wind pressures to be used for exterior component and cladding materials, expressed in pounds per square foot
4. STRUCTURAL CALCULATIONS - ENGINEER'S SEAL: Engineers in Arizona are required to seal, sign, and date construction documents that they prepare for regulatory approval, permitting, or construction. The submitted structural
calculations have not submitted without an engineer's seal. Please revise and resubmit.







Building(B) Reviewer
Kimiyoshi Shimabukuro
kshimabukuro@safebuilt.com
Approved
Reason:
Date Completed : 10/21/2024 4:43:37 AM






Mechanical(M) Reviewer
Jake Doub
jdoub@safebuilt.com
Approved
Reason:
Date Completed : 10/26/2024 8:09:28 PM






Electrical(E) Reviewer
Ron Ross
rross@safebuilt.com
Approved with Comments
Reason:
Date Completed : 10/26/2024 11:03:24 AM
1. E-101 Key Note #2 should be revised to more accurately call out the other 18 contact LCP panel.
2. as two Key Note #5s. Should renumber/remove extra.
3. E-101 should provide missing Key Note 11 description.
4. E-201 Security Key Note S2 is used at numerous locations. Should provide missing Key Note description.







Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Approved
Reason:
Date Completed : 10/28/2024 10:04:59 PM
10/29/2024 Commercial Mechanical APPROVED Structural(S) Reviewer
Madeline Nelson
mnelson@safebuilt.com
Denied
Reason:
Date Completed : 10/24/2024 11:17:55 PM
1. GENERAL - UPDATES: For project updates, please submit sheets with all changes clearly marked in revision clouds. Please provide a written response to each comment; updates without a clear response to all comments may not be
reviewed. If you have any questions regarding the comments, you may contact me directly. Updates may result in additional comments.
2. GENERAL - FIRM REGISTRATION: Per the Arizona Revised Statutes, Chapter 32, Rule 141, a firm shall not engage in the practice of any board-regulated profession or occupation unless the firm is registered with the board”. Please
ensure that Hohbach-Lewin, Inc has been properly registered with the State of Arizona under this provision. Refer to the Arizona State Board of Technical Registration (https://btr.az.gov/public/registered-firm-branch-search) for more
information.
3. S100 - WIND DESIGN CRITERIA: Section 1603.1.4 of the 2018 International Building Code lists the wind design criteria that must be provided on the construction documents. Please revise the structural general notes to include the
following:
i. Basic design wind speed, V, expressed in miles per hour
ii. Wind Exposure
iii. Design wind pressures to be used for exterior component and cladding materials, expressed in pounds per square foot
4. STRUCTURAL CALCULATIONS - ENGINEER'S SEAL: Engineers in Arizona are required to seal, sign, and date construction documents that they prepare for regulatory approval, permitting, or construction. The submitted structural
calculations have not submitted without an engineer's seal. Please revise and resubmit.







Building(B) Reviewer
Kimiyoshi Shimabukuro
kshimabukuro@safebuilt.com
Approved
Reason:
Date Completed : 10/21/2024 4:43:37 AM






Mechanical(M) Reviewer
Jake Doub
jdoub@safebuilt.com
Approved
Reason:
Date Completed : 10/26/2024 8:09:28 PM






Electrical(E) Reviewer
Ron Ross
rross@safebuilt.com
Approved with Comments
Reason:
Date Completed : 10/26/2024 11:03:24 AM
1. E-101 Key Note #2 should be revised to more accurately call out the other 18 contact LCP panel.
2. as two Key Note #5s. Should renumber/remove extra.
3. E-101 should provide missing Key Note 11 description.
4. E-201 Security Key Note S2 is used at numerous locations. Should provide missing Key Note description.







Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Approved
Reason:
Date Completed : 10/28/2024 10:04:59 PM
10/29/2024 Commercial Plumbing APPROVED Structural(S) Reviewer
Madeline Nelson
mnelson@safebuilt.com
Denied
Reason:
Date Completed : 10/24/2024 11:17:55 PM
1. GENERAL - UPDATES: For project updates, please submit sheets with all changes clearly marked in revision clouds. Please provide a written response to each comment; updates without a clear response to all comments may not be
reviewed. If you have any questions regarding the comments, you may contact me directly. Updates may result in additional comments.
2. GENERAL - FIRM REGISTRATION: Per the Arizona Revised Statutes, Chapter 32, Rule 141, a firm shall not engage in the practice of any board-regulated profession or occupation unless the firm is registered with the board”. Please
ensure that Hohbach-Lewin, Inc has been properly registered with the State of Arizona under this provision. Refer to the Arizona State Board of Technical Registration (https://btr.az.gov/public/registered-firm-branch-search) for more
information.
3. S100 - WIND DESIGN CRITERIA: Section 1603.1.4 of the 2018 International Building Code lists the wind design criteria that must be provided on the construction documents. Please revise the structural general notes to include the
following:
i. Basic design wind speed, V, expressed in miles per hour
ii. Wind Exposure
iii. Design wind pressures to be used for exterior component and cladding materials, expressed in pounds per square foot
4. STRUCTURAL CALCULATIONS - ENGINEER'S SEAL: Engineers in Arizona are required to seal, sign, and date construction documents that they prepare for regulatory approval, permitting, or construction. The submitted structural
calculations have not submitted without an engineer's seal. Please revise and resubmit.







Building(B) Reviewer
Kimiyoshi Shimabukuro
kshimabukuro@safebuilt.com
Approved
Reason:
Date Completed : 10/21/2024 4:43:37 AM






Mechanical(M) Reviewer
Jake Doub
jdoub@safebuilt.com
Approved
Reason:
Date Completed : 10/26/2024 8:09:28 PM






Electrical(E) Reviewer
Ron Ross
rross@safebuilt.com
Approved with Comments
Reason:
Date Completed : 10/26/2024 11:03:24 AM
1. E-101 Key Note #2 should be revised to more accurately call out the other 18 contact LCP panel.
2. as two Key Note #5s. Should renumber/remove extra.
3. E-101 should provide missing Key Note 11 description.
4. E-201 Security Key Note S2 is used at numerous locations. Should provide missing Key Note description.







Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Approved
Reason:
Date Completed : 10/28/2024 10:04:59 PM
N/A Bldg Permits - Post Review PENDING ASSIGNMENT
N/A Fire New Construction PENDING ASSIGNMENT
N/A Site Engineering PENDING ASSIGNMENT
N/A Site Zoning PENDING ASSIGNMENT
10/29/2024 Commercial Structural REQUIRES RESUBMIT Structural(S) Reviewer
Madeline Nelson
mnelson@safebuilt.com
Denied
Reason:
Date Completed : 10/24/2024 11:17:55 PM
1. GENERAL - UPDATES: For project updates, please submit sheets with all changes clearly marked in revision clouds. Please provide a written response to each comment; updates without a clear response to all comments may not be
reviewed. If you have any questions regarding the comments, you may contact me directly. Updates may result in additional comments.
2. GENERAL - FIRM REGISTRATION: Per the Arizona Revised Statutes, Chapter 32, Rule 141, a firm shall not engage in the practice of any board-regulated profession or occupation unless the firm is registered with the board”. Please
ensure that Hohbach-Lewin, Inc has been properly registered with the State of Arizona under this provision. Refer to the Arizona State Board of Technical Registration (https://btr.az.gov/public/registered-firm-branch-search) for more
information.
3. S100 - WIND DESIGN CRITERIA: Section 1603.1.4 of the 2018 International Building Code lists the wind design criteria that must be provided on the construction documents. Please revise the structural general notes to include the
following:
i. Basic design wind speed, V, expressed in miles per hour
ii. Wind Exposure
iii. Design wind pressures to be used for exterior component and cladding materials, expressed in pounds per square foot
4. STRUCTURAL CALCULATIONS - ENGINEER'S SEAL: Engineers in Arizona are required to seal, sign, and date construction documents that they prepare for regulatory approval, permitting, or construction. The submitted structural
calculations have not submitted without an engineer's seal. Please revise and resubmit.







Building(B) Reviewer
Kimiyoshi Shimabukuro
kshimabukuro@safebuilt.com
Approved
Reason:
Date Completed : 10/21/2024 4:43:37 AM






Mechanical(M) Reviewer
Jake Doub
jdoub@safebuilt.com
Approved
Reason:
Date Completed : 10/26/2024 8:09:28 PM






Electrical(E) Reviewer
Ron Ross
rross@safebuilt.com
Approved with Comments
Reason:
Date Completed : 10/26/2024 11:03:24 AM
1. E-101 Key Note #2 should be revised to more accurately call out the other 18 contact LCP panel.
2. as two Key Note #5s. Should renumber/remove extra.
3. E-101 should provide missing Key Note 11 description.
4. E-201 Security Key Note S2 is used at numerous locations. Should provide missing Key Note description.







Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Approved
Reason:
Date Completed : 10/28/2024 10:04:59 PM
10/14/2024 PDSD Application Completeness REVIEW COMPLETED