Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Number: TC-COM-1023-02498
Parcel: 141113710

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-1023-02498
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
11/22/2023 Site Engineering APPROVED
11/08/2023 Site Zoning APPROVED
11/20/2023 Water - PDSD APPROVED
11/22/2023 Bldg Permits - Post Review Express PENDING ASSIGNMENT
11/14/2023 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Structural(S) Reviewer
Janet Matz
jmatz@safebuilt.com
Denied
Reason:
Date Completed : 11/14/2023 1:29:15 AM
1. Indicate the required design criteria for the new structure on the drawings including the live and dead loads, designed wind speed and seismic category. Show all wind bracing on the drawings or indicate it will be provided with the metal building differed submittal.


Building(B) Reviewer
Janet Matz
jmatz@safebuilt.com
Denied
Reason:
Date Completed : 11/14/2023 1:27:55 AM
1. It is unknown if the proposed tenant will be storage only or if the space will be used for other purposes such as vehicle repair or hazardous storage. Note on the drawings that additional safety systems may be required depending on the final tenant specific use within the S-1 occupancy classification. Future tenants will comply with all regulations regarding the use as required by the City of Tucson’s adopted codes.

2. Sheet C1.0. Coordinate the sheet index so it matches the drawing sheet numbers. The structural drawings are labeled differently. Update the addresses on the structural drawings to indicate the street number 8219 S Camino De Café Lot 8.

3. Provide an overall section through the building that shows the wall and roof details. Include insulation details for the skylights in the detail or separately.

4. Sheet A1.0. Provide accessibility heights for all of the plumbing fixtures and permanently mounted bath accessories including the toilet, mirror and the utility sink that are in compliance with ICC A117 2009.

5. Sheet A1.0. Indicate on the finish schedule that all interior finishes will be in accordance with 2018 IBC 803.1.

6. Sheet A3.0. Indicate the insulation value of the ceiling on the section that is in accordance with the IECC for the climate area 2. Only an R13 is noted on the elevation keynote 5. 2015 IECC Table 402.

7. Sheet A3.0. The elevation keynote 6 indicates a 4” concrete slab whereas the structural drawings call for 6” concrete. Coordinate the drawings.




Mechanical(M) Reviewer
Janet Matz
jmatz@safebuilt.com
Denied
Reason:
Date Completed : 11/14/2023 1:28:43 AM
1. Sheet M1.0. Provide a mechanical COMcheck or other approved methodology for the project for the new proposed units that is in compliance with the 2018 IECC.

2. Sheet M1.0. Indicate the location of the permanently installed roof ladder or hatch on the roof plans, the roof appears to be greater than 16 feet above grade. 2018 IMC 306.5.


Electrical(E) Reviewer
Janet Matz
jmatz@safebuilt.com
Denied
Reason:
Date Completed : 11/14/2023 1:28:19 AM
1. Provide an interior lighting COMcheck or other approved methodology for the project for the new proposed lighting that is in compliance with the 2018 IECC.

2. Sheet E1.0. Indicate the lighting will be controlled by occupancy sensors. Occupancy sensors are required in offices, bathrooms, and storage/ warehouse areas. 2018 IECC C405.2.1.

3. Although not required (since the space only needs one means of egress and no exit signage), it is recommended that at least one emergency light be provided in the open storage area for illumination in the case of a power failure.



Plumbing(P) Reviewer
Janet Matz
jmatz@safebuilt.com
Approved
Reason:
Date Completed : 11/14/2023 1:28:54 AM
11/02/2023 Fire New Construction REVIEW COMPLETED
10/30/2023 PDSD Application Completeness Express REVIEW COMPLETED