Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.2
Permit Number - TC-COM-1023-02490
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 09/23/2024 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 09/23/2024 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Structural(S) Reviewer (from previous submittal TUC9436002.081324) Madeline Nelson mnelson@safebuilt.com Approved Reason: Date Completed : 8/15/2024 8:50:49 PM Building(B) Reviewer Keith Miller kmiller@safebuilt.com Denied Reason: Date Completed : 9/23/2024 11:47:50 AM 1. Unresolved - General: Verify that all drawings and details related to the splashpad and mechanical room are not included in the notes for exempted work. (2018 IBC section 107) Sheet a7.0 shows the splash pad is removed from the scope of work. 2. Resolved - Sheet g2.0: Update the occupancy load calculations. (2018 IBC section 107) 3. Resolved - Sheet x1.1: Update the area of renovation. (2018 IBC section 107) 4. Unresolved - Sheets s1.0, s1.1, s1.2, s1.3, s2.0, s3.0, s4.0: Update the list of special inspections, drawings, and details pertaining to the revised scope of work. (2018 IBC section 107) ) The page with the list of special inspections was not revised to only include the structures being installed. 5. Resolved - Sheets p1.1, p2.1: Include the plumbing details and diagrams for the splashpad and equipment still part of the scope of work. (2018 IBC section 107) Refer to plumbing reviewer’s comments. 6. Unresolved - Sheets e1.1, e2.1, e3.1, e4.1, e4.2: Include all electrical plans and details still relevant to the splashpad, equipment, and lighting still part of the scope of work. New subpanel “A1” feeds circuits that may still be present including the splashpad equipment. Show or detail the routing of the new circuits and feeders to determine if located above the ceiling. Revise and update the electrical load calculations. (2018 IBC section 107) Electrical schedules and details were specified as not included in the scope instead of being revised. Please update all electrical drawings, details, schedules, calculations, etc. to reflect the revised plans. Mechanical(M) Reviewer (from previous submittal TUC9436002.081324) Jorge Valido jvalido@safebuilt.com Approved Reason: Date Completed : 8/19/2024 2:25:05 PM 1. Condition - As per Revision letter Dated August 12, 2024, The Salvation Army is not pursuing the interior remodel nor replacement of rooftop mechanical units shown in alternate one. The existing building is to remain as is, with exception to the renovation of the former women’s shower room into a mechanical room for the splashpad. Electrical(E) Reviewer (from previous submittal TUC9436002.081324) Ron Ross rross@safebuilt.com Approved Reason: Date Completed : 8/14/2024 3:19:20 PM Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Approved with Comments Reason: Date Completed : 9/22/2024 11:15:20 PM Copy to clipboard2nd revised Plan Plumbing Review:( removing interior remodel work) ok subject to field inspections RESOLVED-1). General: Need to address building plan review comments 3 & 5- 2018 IPC 106.3.1 RESOLVED-2). Plan Page P1.1 Detail 2: Missing backflow device for splash pad main water feed., add backflow device in accordance with -2018 IPC 608.3 RESOLVED-3). Plan page P2.1: per revision narrative states interior remodel not taking place? Remove items & illustrations from plan page P2.1 that are no longer relevant- 2018 IPC 106.3.1 |
||
| 09/18/2024 | PDSD Application Completeness Express | REVIEW COMPLETED |