| 02/09/2024 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 01/17/2024 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Structural(S) Reviewer Madeline Nelson mnelson@safebuilt.com Approved Reason: Date Completed : 1/15/2024 1:46:01 PM Building(B) Reviewer Keith Miller kmiller@safebuilt.com Denied Reason: Date Completed : 1/11/2024 2:21:34 PM 1) Resolved - General: Show accessible routes from parking spaces through building. Inconsistent accessible parking spaces shown on the site plan and other sheets. Please coordinate and revise drawings. (2009 ICC A117.1 Chapter 4) 2) Unresolved - General, Sheet A9.0: Include the wall, ceiling, roof, foundation, and fenestration energy code compliance details matching the entries in the COMcheck envelope. Revise all applicable sheets. (2018 IECC section C402) The COMcheck specifies the walls have cavity insulation of R-21 but the plans only show R-19. Only EIFS walls with continuous insulation are included in the COMcheck but the plans show walls with metal siding and no continuous insulation. 3) Resolved - Sheet g2.0 (Egress Plan): Provide the means of egress travel path distances. (2018 IBC section 107, 1017) 4) Resolved - Sheets a1.0, a7.0: Show the plumbing fixture accessible clear floor spaces and include the dimensions. (2009 ICC A117.1 sections 305.3, 604.3, 604.9) 5) Resolved - Sheets a1.0, a7.0: Toilet room door swings into the toilet clear floor space. (2009 ICC A117.1 section 603.2.2) 6) Resolved - Sheets a1.0, a7.0: Show the maneuvering clearance spaces at the doors as required by 2009 ICC A117.1 sections 404.2.3, 404.3.2, Table 404.2.3.2. Include the dimensions on the latch side of recessed doors. 7) Unresolved - Sheet a1.0 (Floor Plans): Show the accessible auditorium and dining seating. (2009 ICC A117.1 sections 802 and 902) Accessible dining seating is required to be provided for fixed or movable dining surfaces. 8) Unresolved - Sheet a8.0 (Window and Door Details): Include the door hardware and closers in the door schedule, window schedule, and detail safety glazing in windows and doors. (2018 IBC section 2406) The door hardware note numbers do not correspond to any notes on the sheet. The window schedule was not included in the revised plans. Mechanical(M) Reviewer Jorge Valido jvalido@safebuilt.com Approved Reason: Date Completed : 1/11/2024 11:15:14 AM 1. Plan Sheet M1.0 under Key Notes #11 and #12 Should be See 1/ M1.1 - See 2/ M1.1 - 2018 IBC – Section [A]107.2.1Information on construction documents.(RESOLVED) 2. General - Provide Mechanical General Notes. Provide General Notes for Duct Work, Rigid/Flexible, Supply, Return, Exhaust Criteria, (type), Insulation exterior/Interior Liner (type), Equipment requirements, Installation and Testing of all Equipment, Test and Balance requirements, HVAC Symbols, HVAC Abbreviations, Supports, Anchors, Sleeves, Fire and or Fire/Smoke Damper Criteria, etc... - 2018 IBC – Section [A]107.2.1Information on construction documents. (RESOLVED) 3. Provide on Plan Sheet M4.0 diagram/drawing of duct support/hanging detail. - 2018 IBC – Section [A]107.2.1Information on construction documents.(RESOLVED) Electrical(E) Reviewer Ron Ross rross@safebuilt.com Approved Reason: Date Completed : 11/10/2023 2:10:37 PM Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Approved with Comments Reason: Date Completed : 1/17/2024 10:27:49 AM Second Plumbing Review: OK Subject To Field inspections Resolved-1). Need to address Building Plan Review Comments 4 & 5 -IPC 404.1 Resolved-2). Washer drain line needs to connect to 3" branch on plan pages P1.0 & P2.0 -IPC 406.2 Resolved-3). Coffee shop drains need to discharge thru a grease interceptor on plan pages P1.0 & P2.0 or provide letter from utility authority stating not required. -Tucson Plumbing code amendments** SEE ATTACHED EMAIL CHAIN FROM UTILITY AUTHORITY ALLOWING GREASE TRAP TO NOT BE REQUIRED** Resolved-4). The location of primary & secondary scuppers for roofs B & C on plan page A3.0 not clear -IPC 1101.7 Resolved-5). Provide Roof draining method detail for area D on plan page A3.0 -IPC 1110, 1113 Resolved-6). Add piping materials to plan page P3.0 -IPC 106.3.1 |
||
| 02/09/2024 | Fire New Construction | REQUIRES RESUBMIT | Resolve all building comments. john.vincent@tucsonaz.gov 5203495581 |
||
| 02/06/2024 | Site Engineering | REQUIRES RESUBMIT | See zoning comment | ||
| 01/12/2024 | Site Zoning | REQUIRES RESUBMIT | FROM: PDSD Zoning Review Section PROJECT: TC-COM-1023-02478 9455 E VALENCIA RD - SR New Auditorium and office building (2nd Review) TRANSMITTAL DATE: January 12, 2024 COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This site is located in the SR zone (UDC 4.7.4). A Religious use is a permitted use in the zone (UDC Table 4.8-1). 1. COMMENT: Zoning has reviewed the building plan for compliance with TD-DEV-0823-00354, and although it appears that the plan match, Zoning cannot approve the building plans until the DP is approved by all review agencies. If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov. |
||
| 01/10/2024 | PDSD Application Completeness Express | REVIEW COMPLETED |