Permit Number: TC-COM-1023-02456
Parcel: 11203287A

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-1023-02456
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
11/08/2023 Commercial Mechanical APPROVED
11/08/2023 Commercial Plumbing APPROVED
10/24/2023 Site Zoning APPROVED
11/06/2023 Site Engineering NOT REQUIRED
11/15/2023 Bldg Permits - Post Review Express PENDING ASSIGNMENT
11/15/2023 Commercial Electrical REQUIRES RESUBMIT Please address the electrical plan review comments and provide a written response.

1. This is considered a commercial project. Please remove references to the 2018 IRC and replace with references to the 2017 NEC.

2. Relocate Breaker panels in both units to a code compliant location. NEC art 240.24(D), 240.24(E), 408.17.

3. If the exterior lighting is to be replaced, provide full compliance with the 2012 City of Tucson Outdoor Lighting Code.

4. Revise the power requirements for the AC systems and revise the electrical load calculations accordingly. See Mechanical Equipment schedule for AC power specs.

Ref; 2018 IBC section 107.2.1, 2017 NEC.
11/15/2023 Commercial Structural REQUIRES RESUBMIT Submit your revised drawings along with a detailed response letter, which states how all Building Review Section comments were addressed.
1. The structural (Starling, Madison, Lofquist, Inc.) engineer's fire damage investigation enumerated structural fire damage on roof rafters/sheathing/framing members, party separation walls wood studs/top & bottom plates, structurally fire damaged dropped ceiling joists, interior separation walls between bathroom and kitchen, etc. Structural members being removed and replaced. This apply for both Unit 524 and 525.
2. Submit the stamped repair drawings done by the structural engineer as mentioned in their report.
3. Locate the fire damaged areas needing repair on your drawings, provide detail drawings supporting how the repairs are being addressed.
4. Please resubmit.
10/24/2023 Fire New Construction REVIEW COMPLETED
10/24/2023 PDSD Application Completeness Express REVIEW COMPLETED