Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-1023-02386
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
10/18/2023 Site Zoning APPROVED
11/02/2023 Water - PDSD APPROVED
10/30/2023 Site Engineering NOT REQUIRED
11/02/2023 Bldg Permits - Post Review Express PENDING ASSIGNMENT
10/18/2023 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Structural(S) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 10/18/2023 10:43:04 AM
See the building review comments.



Building(B) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 10/18/2023 10:41:28 AM
1) Sheet A0.0 (Cover Sheet): The plumbing fixture calculations incorrectly show the number of male/female occupants. 40 occupants are to be equally divided making 20 men and 20 women. (2018 IPC section 403.1.1)

2) Sheets A2.0 and P1.0: A floor drain is detailed on the floor plan, but it has not been included in the plumbing diagrams and sheets. (2018 IBC section 107)

3) Sheet A5.0 (Door Details): Include the U-Factors of the doors meeting the requirements of the 2018 IECC section C402.4




Mechanical(M) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 10/18/2023 10:42:26 AM
See the building review comments.




Electrical(E) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 10/18/2023 10:42:03 AM
See the building review comments.



Plumbing(P) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 10/18/2023 10:42:46 AM
See the building review comments.
10/27/2023 Fire New Construction REVIEW COMPLETED
10/12/2023 PDSD Application Completeness Express REVIEW COMPLETED