Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0926-01597
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 10/15/2026 | Outdoor Lighting Standard | APPROVED | |||
| 10/19/2026 | Commercial Post Review Express | PENDING ASSIGNMENT | |||
| 10/19/2026 | Commercial Building Standard | REQUIRES RESUBMIT | 1. Please provide the signed and sealed structural calculations, prepared by an Arizona licensed registrant, used in the design of this project. IBC 107.2.7 If you have any questions regarding these comments, please contact me. Mark Masek Plans Examiner – Building Safety Planning and Development Services City of Tucson Main: 520.837.4994 Email: mark.masek@tucsonaz.gov |
||
| 10/15/2026 | Commercial Electrical Standard | REQUIRES RESUBMIT | Commercial Electrical Review TC-COM-0926-01597 (2711 S HOUGHTON RD TUCSON, AZ 85730) Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. Provide updated Plans/calculations and a written response Letter to each of the notated items indicating action taken. Resubmitted plans that do not contain a written response Letter addressing each of the notated items indicating action taken, may be delayed until response letter is received. Code reference, 2024 International Building Code (IBC), 2023 National Electrical Code (NEC), 2012 Outdoor Lighting Code (OLC). https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/building-code/2012_outdoor_lighting_code_.pdf Contact Jeremy Hamblin with any questions: Jeremy.hamblin@tucsonaz.gov 1. Reference sheet E2.0, Conductor/conduit ID #1. The provided conductors are undersized for the given 2,500A OCPD setting of the main breaker. The ampacity of the conductors shall be equal to or greater than the rating of the overcurrent device, NEC 240.4(C). |
||
| 10/02/2026 | Site Engineering Standard | REQUIRES RESUBMIT | Permit Activity Number: TC-COM-0926-01597 (1st Review) Project: Exterior Parking Canopy Location: Install 4 Level 3 EV Charging Stations in the existing Walmart Parking lot Review Date: 10/02/2026 Reviewer: John Mounsey – Engineering Associate Reviewer Contact Information: john.mounsey@tucsonaz.gov Site Engineering comments are as follows: 1. Development Package Required: The proposed parking canopy at this commercial site requires the submittal of a Development Package (site plan) in accordance with UDC §7.4.3.E. Per UDC §3.3.3.G.2.c, a Development Package (DP) meeting the requirements of the Checklist for Minor Changes to Commercial/Industrial Sites must be submitted and approved. The Development Package is a separate submittal from the building plans and must be processed independently. 2. Site Engineering Review: Site Engineering is unable to fully review and approve permit TC-COM-0926-01597 until the associated Development Package has been reviewed and approved by all applicable reviewers. |
||
| 10/19/2026 | Site Zoning Standard | REQUIRES RESUBMIT | PDSD TRANSMITTAL FROM: Jeffrey W. Cassidy, Planner I Planning & Development Services Department – Current Zoning Review Section, Commercial PROJECT: TC-COM-0926-01597– Commercial – Install 4 Level 3 EV Charging Stations in the existing Walmart Parking lot 2711 S HOUGHTON RD TUCSON, AZ 85730 (C-1 Zoning) Commercial Building Plan Review – 1st Review TRANSMITTAL DATE: October 19, 2026 1. COMMENT: Per UDC Article 3.3.3.G.2.c, a site plan (Development Package) is required for the following types of development: Existing development undergoing a change of use, building structure additions, and/or a reconfiguration of an area outside a building. A Development Package (DP) meeting the requirements of the Checklist for Minor Changes to Commercial/Industrial Sites is required to be submitted and approved (the same checklist is used for ‘major’). The DP is a separate submittal from the building plans. Code reference to format submittal to and comply with: https://codelibrary.amlegal.com/codes/tucson/latest/tucson_az_udc/0-0-0-8753 The checklist can be found at: https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/minor_changes_to_commercial_industrial_sites_.pdf. For final building permit approval, ensure the building plans match the eventual approved DP, regarding footprint, proposed height, and square footage, and that the downspout and structure drainage systems shown in the building plans are consistent with those depicted in the Development Package plan set. The development package must be approved prior to the building permit receiving its approval. 2. COMMENT: As there will be a subtraction of nine parking spaces, include an updated parking calculation for the entire site and all the existing uses on the site on the development package. Include the number required and provided. 3. COMMENT: Additional comments may be forthcoming on the next review based on responses to Zoning and other PDSD reviewer comments. RESUBMITTAL OF THE FOLLOWING IS REQUIRED: 4. COMMENT: Corrected commercial building permit (if applicable from any changes on future development package permit). 5. COMMENT: Provide a detailed response letter with your submittal that clearly shows how you have addressed all Zoning comments. To resubmit visit Tucson Development Center at https://tdc-online.tucsonaz.gov/#/home . Instructions for resubmittal - https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/tdc-faq/old-pdfs/double-old/resubmittals.pdf If you have any questions about this transmittal, please contact jeffrey.cassidy@tucsonaz.gov The Unified Development Code (UDC) can be found at: https://www.tucsonaz.gov/Departments/Planning-Development-Services/Codes/Zoning-Code . |
||
| 10/14/2026 | Fire New Construction Standard | REVIEW COMPLETED | |||
| 09/29/2026 | PDSD Application Completeness Express | REVIEW COMPLETED |