| 10/09/2025 | Outdoor Lighting Standard | APPROVED | |||
| 10/16/2025 | Water - PDSD Standard | APPROVED | |||
| 10/24/2025 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 10/13/2025 | Commercial Building Standard | REQUIRES RESUBMIT | Structural(S) Reviewer Andrew Frame aframe@safebuilt.com Denied Reason: Date Completed : 10/13/2025 12:20:41 PM 10/13/2025 Review Requires Resubmittal AFrame: 1. Sheet S100: GEOTECHNICAL REPORT 29-225001-0 PREPARED BY WESTERN TECHNOLOGIES. DATED MARCH 12, 2025 is referenced. Please provide GEOTECHNICAL REPORT 29-225001-0 PREPARED BY WESTERN TECHNOLOGIES. DATED MARCH 12, 2025. Please provide GEOTECHNICAL REPORT 29-225001-0 and resubmit for review. Building(B) Reviewer Andrew Frame aframe@safebuilt.com Denied Reason: Date Completed : 10/13/2025 12:23:01 PM 10/13/2025 Review Requires Resubmittal AFrame: 1. Sheet T2.0-General Building Summary: R-2 Occupancy is the only Occupancy type listed. Sheet T3.0 Shows a B Occupancy for the office, an A-3 Occupancy for the Gym, Movie Theatre, and Game Room and gather area, and S-2 Occupancy for Storage. Please include these Occupancies on the General Building Summary on Sheet T2.0 and resubmit for review. 2. Sheet T2.0: GA file WP 3661 is referenced for Corridor Wall construction. Please provide full /complete GA file WP 3661 details on plans and resubmit for review. 3. Sheet T2.0: UL L521 is referenced for Floor and Ceiling construction. Please provide full /complete UL L521 details on plans and resubmit for review. 4. Sheet S100: GEOTECHNICAL REPORT 29-225001-0 PREPARED BY WESTERN TECHNOLOGIES. DATED MARCH 12, 2025 is referenced. Please provide GEOTECHNICAL REPORT 29-225001-0 PREPARED BY WESTERN TECHNOLOGIES. DATED MARCH 12, 2025. Please provide GEOTECHNICAL REPORT 29-225001-0 and resubmit for review. 5. Sheet A2.0-Wall Types: 7: UL U415 SYSTEM B is referenced for 2 Hour Rated Shaft Wall Construction. Please provide full /complete UL U415 SYSTEM B details on plans and resubmit for review. 6. notations from plans if no elevator is to be installed and resubmit for review. 7. Sheets A9.1, A2.0, A2.1, A2.2, A2.3, 2.4, and A2.5: Please indicate which window(s) meets the requirements of IBC 1031 for Emergency Escape and Rescue Openings for each sleeping room and resubmit for review. The window schedule does not address this. |
||
| 10/13/2025 | Commercial Electrical Standard | REQUIRES RESUBMIT | Electrical(E) Reviewer Ron Ross rross@safebuilt.com Denied Reason: Date Completed : 10/9/2025 7:11:32 PM 1. E0.5 ELECTRICAL EXTERIOR LIGHTING CUTSHEETS & COMCHECK: Missing interior lighting comcheck. 2. E3.0 ENLARGED ELECTRICAL LIGHTING PLAN - LEVEL 1: Missing an interior lighting comcheck for this specific area. 3. E3.1 ENLARGED ELECTRICAL POWER PLAN - LEVEL 1: Could not locate Keyed Note 22. 4. E3.2 ENLARGED ELECTRICAL FLOOR PLANS: Keyed Note 11 calls out design location of Media panel to be under the electrical panel. This violates NEC 110.26(E) code requirements for dedicated working space of power panels. Space directly above and below the power panel are reserved for circuits to enter into the power panel and cannot be obstructed by any panels or equipment that cannot function as a raceway for circuits entering or leaving the power panel. A low voltage media panel does not meet this requirement and therefore cannot be mounted below the power panel. Relocate media panel to another location. 5. E4.0 ELECTRICAL ONE-LINE DIAGRAM: Confirm underground primary requirement for (9) 4” conduits. The primary side of a medium voltage transformer typically only requires a couple of feeders. 6. E4.1 ELECTRICAL PANEL SCHEDULES: Trip rating in SES-HP for Panel P2A should be 100 amps as per One-Line on sheet E4.0. 7. E4.2 ELECTRICAL PANEL SCHEDULES: Comment only, Multi-Meter Load Calculations could have used 26% as per NEC Table 220.84. |
||
| 10/13/2025 | Commercial Mechanical Standard | REQUIRES RESUBMIT | Mechanical(M) Reviewer Jorge Valido jvalido@safebuilt.com Denied Reason: Date Completed : 10/6/2025 1:18:01 PM 1. General - Plan Sheet M1.0 & M2.0 FCU A-1 total CFM at the supply air grills/diffusers ais 766 CFM. Plan Sheet M0.2 states on the VARIABLE REFRIGERANT FLOW FAN COIL UNIT SCHEDULE for FCU A-1 "Supply Fan Airflow (CFM) 625. Confirm Total CFM for FCU A-1 at the Supply air grills/diffusers. - 2018 IECC Section C103.2Information on construction documents - 2018 IBC Section [A]107.2.1Information on construction documents. 2. General - Plan Sheet M2.0 FCU B-1 total CFM at the supply air grills/diffusers ais 1550 CFM. Plan Sheet M0.2 states on the VARIABLE REFRIGERANT FLOW FAN COIL UNIT SCHEDULE for FCU B-1 "Supply Fan Airflow (CFM) 2000. Confirm Total CFM for FCU B-1 at the Supply air grills/diffusers. - 2018 IECC Section C103.2Information on construction documents - 2018 IBC Section [A]107.2.1Information on construction documents. 3. General - Plan Sheet M1.2 FCU A-3 total CFM at the supply air grills/diffusers ais 796 CFM. Plan Sheet M0.2 states on the VARIABLE REFRIGERANT FLOW FAN COIL UNIT SCHEDULE for FCU A-3 "Supply Fan Airflow (CFM) 625. Confirm Total CFM for FCU A-3 at the Supply air grills/diffusers. - 2018 IECC Section C103.2Information on construction documents - 2018 IBC Section [A]107.2.1Information on construction documents. 4. General - Provide refrigerant routing on plans. Provide riser details - 2018 IECC Section C103.2Information on construction documents - 2018 IBC Section [A]107.2.1Information on construction documents. 5. General - A2L type refrigerants require ASHRAE 15 calculations for each type design using A2L type refrigerants. Refrigerant shafts vented (naturally or mechanically) may be required when routing refrigerant lines through floors. Monitoring systems with alarms may also be required. - 1109.3 Installation requirements for A2L and B2L refrigerants. 1109.2.5 Refrigerant pipe shafts. 1109.3.2 Shaft ventilation. 1109.2.4 Piping in concrete floors. 1109.5 Refrigerant pipe penetrations .1109.8.1 Refrigerating systems containing more than 6.6 pounds (3.0 kg) of refrigerant. 1109.3.3 Pipe identification. 1109.3.1 Pipe protection. ASHRAE 15 and ASHRAE 34. - 2018 IMC - 2018 IECC Section C103.2Information on construction documents. - 2018 IBC Section [A]107.2.1Information on construction documents. |
||
| 10/13/2025 | Commercial Plumbing Standard | REQUIRES RESUBMIT | Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Denied Reason: Date Completed : 10/12/2025 2:36:13 PM First Plumbing Review: 1). Plan Page P3.0 details 2,4,5,6,7: The Waste Stack/Vent must remain full size thru roof. Edit the Waste Stack/Vent size to remain the same size or lager as it originates at the ground thru the roof level. -2018 IPC 913.3, 913.4 |
||
| 10/15/2025 | Fire New Construction Standard | REQUIRES RESUBMIT | 1. Sheet T2.0, applicable codes. COT/TFD has adopted the 2024 IFC. Please make correction to your applicable codes. 2. Please make a note that the fire alarm will be installed in accordance with IFC 907.2.9 and NFPA 72. 3. Resolve all building comments. john.vincent@tucsonaz.gov 5203495581 |
||
| 10/07/2025 | Site Engineering Standard | REQUIRES RESUBMIT | Permit: TC-COM-0925-01751 Location: 855 W Prince RD Review Date: 10/7/2025 Site Engineering Comments: 1. Site Engineering will be unable to review and approve permit TC-COM-0925-017451until the associated development package TD-DEV-0925-00236 is reviewed and approved by all reviewers. If you have any questions or concerns, please contact Marco Contreras Marco.contreras@tucsonaz.gov |
||
| 10/24/2025 | Site Zoning Standard | REQUIRES RESUBMIT | PDSD TRANSMITTAL FROM: Bobby Parsons Zoning Section Review PROJECT: TC-COM-0925-01751 855 W. Prince Rd. Tucson, AZ 85705 3 Story Apartment Building (1st Review) TRANSMITTAL DATE: 10/24/2025 The site is in the C-2 zone (UDC 4.7.21). Multifamily is a permitted use in the C-2 zone. Comments: Please resubmit revised drawings along with a detailed response letter which states how all Zoning Review Section comments were addressed. 1. Comment: Zoning has conducted a cursory review of the building permit and while it appears the site plan is consistent with the development package, Site Zoning cannot approve this building permit until the associated development package (TD-DEV-0924-00246) has been approved by all reviewers. We are requiring a revision to TD-DEV-0924-00246 as this project will be reviewed as one site. Please ensure the building plans provided match what is being reviewed in the development package revision. 2. Comment: Additional comments may be forthcoming based on responses to zoning comments and plans submitted. If you have any questions about this transmittal, please contact Bobby Parsons at Robert.Parsons@tucsonaz.gov. |
||
| 09/25/2025 | PDSD Application Completeness Express | REVIEW COMPLETED |