Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0925-01698
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 10/06/2025 | Commercial Mechanical Standard | APPROVED | Mechanical(M) Reviewer Jorge Valido jvalido@safebuilt.com Approved Reason: Date Completed : 9/30/2025 11:49:15 AM |
||
| 10/06/2025 | Commercial Plumbing Standard | APPROVED | Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Approved Reason: Date Completed : 10/4/2025 9:35:45 PM FIRST PLUMBING REVIEW: OK |
||
| 10/01/2025 | Outdoor Lighting Standard | APPROVED | |||
| 10/09/2025 | Water - PDSD Standard | APPROVED | |||
| 10/20/2025 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 10/06/2025 | Commercial Building Standard | REQUIRES RESUBMIT | Structural(S) Reviewer Madeline Nelson mnelson@safebuilt.com Approved Reason: Date Completed : 9/28/2025 5:22:35 PM Building(B) Reviewer Andrew Bevis abevis@safebuilt.com Denied Reason: Date Completed : 9/25/2025 2:57:49 PM 1. Sheet CR-2/Travel Distance: The occupant loads on 2nd through 4th floors require two exits. These exits have been provided, however, one of the exits is considered an exit access stairway. This is not considered an exit and thus the travel on the stairs would need to be included in the travel distance calculation. Provide updated travel distance calculations. (2018 IBC Section 1017.3) 2. General/Listed Assemblies: You may revise this detail to reference a generic Gypsum Association listed assembly, or use an assembly from 2018 IBC Sec. 721.1, with the table and assembly number noted on the detail. Otherwise, UL fire resistant wall assemblies typically use proprietary materials as part of the testing process for the listing. Please provide the most recently published complete for all listed assemblies. Provide one of the following options embedded within the plan set: ◦ Revise to provide a generic Gypsum Association listed assembly versus a UL listed assembly that relies on proprietary materials to create the assembly. (2018 IBC Sec. 703.2 & Sec. 703.3 #1) ◦ Revise to provide a wall section detail designed to show compliance with 2018 IBC Sec. 721.1 and Table 721.1 (2). The detail must clearly show all components to field construct the assembly, with a reference to the table and the item number. (2018 IBC Sec. 703.3 #2) ◦ Revise to provide a wall section detail designed to show compliance with 2018 IBC Sec. 722.1. The detail must clearly show all components to field construct the assembly, with a reference to the table and the item number. (2018 IBC Sec. 703.3 #3) ◦ Since UL utilizes proprietary materials as part of the testing process for the listing. Please provide the most recently published complete UL listed assembly. (2018 IBC Sec. 703.2 & Sec. 703.3 #1) 3. General/Thru Penetration Firestopping: Provide listed through penetration firestopping assemblies. These listed assemblies rely on the use of proprietary materials as part of the testing process to verify the through penetration firestopping assembly listing. Please provide the most recently published complete UL listed assemblies. This will require that you cut and paste the most recently published complete assemblies for embedment within the plan set. (2018 IBC Sec. 714.4.1.2 & Sec. 714.5.1.2) 4. General/Wall Sections: The wall sections for the fire walls have not been provided. Provide walls sections for the fire walls. |
||
| 10/06/2025 | Commercial Electrical Standard | REQUIRES RESUBMIT | Electrical(E) Reviewer Ron Ross rross@safebuilt.com Denied Reason: Date Completed : 10/2/2025 7:19:23 PM 10-2-2025 1. E1.20 2ND + 3RD FLOORS POWER + LIGHTING PLANS: Need to provide circuit information for both power and lighting. 2. E1.21 4TH FLOOR + ROOF POWER + LIGHTING PLANS: No work shown. Call out that no work is needed and shown for reference only if keeping this sheet in submittal. 3. E1.30 1ST FLOOR LIGHTING PLAN: New work is not identified. No lighting controls or circuits shown. 4. E2.01 LIGHTING DETAILS & SCHEDULES: Only exterior lighting calculations performed. Confirm there is no interior lighting. 5. 6 out of 7 panel schedules are empty. Confirm other panels are not used or are installed without circuits. Panels 2A and 3A are shown as New, but E2.20 shows as existing. Coordinate/correct as appropriate. 6. E2.10 PANEL SCHEDULES: Panel 136 is called out as a 3-phase panel, but panel schedule, transformer, and sheet E2.20 show a 1 phase panel. Correct as appropriate. |
||
| 10/07/2025 | Fire New Construction Standard | REQUIRES RESUBMIT | -TFD/COT has already adopted the 2024 IFC. Please make correction to code review, sheet CR1. -A building fire alarm is required per IFC 907.2.2/907.2.7.1. Indicate you will be installing a building fire alarm per IFC 907/NFPA 72. john.vincent@tucsonaz.gov 5203495581 |
||
| 10/17/2025 | Site Engineering Standard | REQUIRES RESUBMIT | TC-COM-0925-01698 440 N 7TH AV Site Engineering Comments are as follows: 1. This commercial building permit cannot be approved until the development package, TD-DEV-0425-00121, is approved by all reviewers. Please see that the comments left by the building reviewers are addressed, as well. UDC Article 3.3.3.7 Ryan Insalaco Engineering Associate ryan.insalaco@tucsonaz.gov |
||
| 10/20/2025 | Site Zoning Standard | REQUIRES RESUBMIT | PDSD TRANSMITTAL FROM: Bobby Parsons Zoning Section Review PROJECT: TC-COM-0925-01698 440 N. 7th Ave. Tucson, AZ 85705; I-1 Tenant Improvement w/ Site Improvements (1st Review) TRANSMITTAL DATE: 10/20/2025 This site is zoned I-1 (UDC 4.7.29). Comments: Please resubmit revised drawings along with a detailed response letter which states how all Zoning Review Section comments were addressed. 1. Comment: Zoning has reviewed the plans for compliance with the associated Development Package (DP) TD-DEV-0425-00121, and although it appears that the building plans are in compliance, until the DP is approved by all review agencies Zoning cannot approve this permit. 2. Comment: Additional comments may be forthcoming depending on responses to zoning review comments and plans submitted. If you have any questions about this transmittal, please contact Bobby Parsons at Robert.Parsons@tucsonaz.gov. |
||
| 09/19/2025 | PDSD Application Completeness Express | REVIEW COMPLETED |