Permit Number: TC-COM-0923-02127
Parcel: 108213300

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0923-02127
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
09/27/2023 Site Zoning APPROVED
10/03/2023 Water - PDSD APPROVED
09/13/2023 Site Engineering NOT REQUIRED
10/03/2023 Bldg Permits - Post Review PENDING ASSIGNMENT
09/07/2023 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Structural(S) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 9/7/2023 2:17:30 PM
See the building review comments.



Building(B) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 9/7/2023 2:15:56 PM
1) General: Include the calculations for the minimum number of toilet room & drinking fountain plumbing fixtures and the separate facilities for the number of occupants served by the toilet rooms. The women's toilet room is being removed. (2018 IPC section 403)

2 Sheet EP101 (Electrical Power Drawings): Panel "P1" is detailed as existing but is shown on a new wall of the addition. Please include the panel schedule and include it on the one-line diagram on sheet EP701. (2018 IEBC section 106)

3) Sheet EP101 (Electrical Power Drawings): Device labeled #5 is detailed as existing but is shown on a new wall of the addition. (2018 IEBC section 106)

4) Sheet EP701 (Electrical Schedules and One-Line Diagram): Show the new or existing earth ground at the separate building. (2017 NEC section 250.32)

5) Sheet EP701 (Electrical Schedules and One-Line Diagram): The one-line diagram
shows the subpanels are fed with 4 conductors along with a ground - the panel schedules show the service is 120/240V single phase. Please coordinate the Wire
& Conduit Schedule with the service and feeder conductors. (2018 IEBC section 106)

6) Sheet m2.01 (Mechanical Equipment Schedules): The schedules show the HVAC equipment is 208V but the electrical sheets show that the service is 120/240V. Please coordinate the mechanical and electrical details. (2018 IEBC section 106)

7) Sheet m2.01 (Mechanical Equipment Schedules): Include the air balancing/combustion air calculations and the dryer specifications for the BTU's and exhaust CFM. (2018 IFGC section 614.6, 304)

8) Sheet a2.01 (Elevation Views): Show the dryer exhaust vents and their distances to the building openings and intakes. (2018 IFGC section 501.3)



Mechanical(M) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 9/7/2023 2:17:00 PM
See the building review comments.



Electrical(E) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 9/7/2023 2:16:39 PM
See the building review comments



Plumbing(P) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 9/7/2023 2:17:15 PM
See the building review comments.
09/11/2023 Fire New Construction REVIEW COMPLETED
09/01/2023 PDSD Application Completeness REVIEW COMPLETED