Permit Number: TC-COM-0826-01254
Parcel: 127090180

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - LIMITED v.1

Permit Number - TC-COM-0826-01254
Review Name: COMMERCIAL REVIEW - LIMITED v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
08/24/2026 Commercial Building APPROVED
08/18/2026 Commercial Electrical APPROVED
08/24/2026 Water - PDSD APPROVED
08/24/2026 Bldg Permits - Post Review Express PENDING ASSIGNMENT
08/24/2026 Commercial Mechanical REQUIRES RESUBMIT ACTIVITY NO. TC-COM-0826-01254
ADDRESS/PARCEL: 6105 E BROADWAY BL TUCSON, AZ 85711

Submit your revised drawings along with a detailed response letter, which states how all comments were addressed. Review will not proceed without the response letter. The submitted documents were incomplete and a thorough plan review could not be performed. Please be aware, new comments may arise with the next review.

If you have any questions about these review comments, I can be reached at Sean.Severson@tucsonaz.gov.

COMMENTS:

1. Please provide an air balance schedule showing the total supply and exhaust airflow quantities for the building. Demonstrate that the proposed HVAC systems maintain the 150 CFM net positive building pressure. Reference: Section 508.1.3, IMC 2024.
08/24/2026 Commercial Plumbing REQUIRES RESUBMIT ACTIVITY NO. TC-COM-0826-01254
ADDRESS/PARCEL: 6105 E BROADWAY BL TUCSON, AZ 85711

Submit your revised drawings along with a detailed response letter, which states how all comments were addressed. Review will not proceed without the response letter. The submitted documents were incomplete and a thorough plan review could not be performed. Please be aware, new comments may arise with the next review.

If you have any questions about these review comments, I can be reached at Sean.Severson@tucsonaz.gov.

COMMENTS:

1. The Demo Plan, Floor Plan, and Kitchen Schedule (Sheet P1.0) show the existing 4-vat fryer being relocated. However, Note M2 on Sheet M1.4 indicates that new gas piping is to be provided for a new 3-vat fryer. Please clarify whether the existing 4-vat fryer is being relocated or replaced with a new 3-vat fryer. Reference: Section 107.2.1, IBC 2024.
08/17/2026 Fire New Construction REVIEW COMPLETED
08/11/2026 PDSD Application Completeness Express REVIEW COMPLETED