Permit Number: TC-COM-0825-01580
Parcel: 13338005E

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0825-01580
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
09/18/2025 Commercial Building Standard APPROVED
09/08/2025 Commercial Electrical Standard APPROVED
09/18/2025 Commercial Mechanical Standard APPROVED
09/19/2025 Site Zoning Standard APPROVED
09/18/2025 Water - PDSD Standard APPROVED
09/08/2025 Outdoor Lighting Standard NOT REQUIRED No modifications to the outdoor lighting.
09/12/2025 Site Engineering Standard NOT REQUIRED
09/19/2025 Bldg Permits - Post Review Express PENDING ASSIGNMENT
09/18/2025 Commercial Plumbing Standard REQUIRES RESUBMIT 1. The plumbing specifications call out a point-of-use, storage type water heater. Where is this located? Reference: Section 107.2.1, IBC 2018.
2. Emergency showers and eyewash stations shall be supplied with tempered water (60-100 degrees Fahrenheit) using a thermostatic mixing valve listed to ASSE 1071, not ASSE 1070. Reference: Section 411.3, IPC 2018.
3. Verify that the installation of the new misting system includes a reduced pressure backflow prevention assembly to protect the water distribution system. Reference: Section 608.17.6, IPC 2018.
4. Provide a direct connection for the floral sink (Keynote 5, P1.1). Reference: Sections 301.3 and 802.1, IPC 2018.
09/17/2025 Fire New Construction Standard REVIEW COMPLETED
08/26/2025 PDSD Application Completeness Express REVIEW COMPLETED