Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0824-01636
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 09/23/2024 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 09/03/2024 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Structural(S) Reviewer Keith Miller kmiller@safebuilt.com Approved Reason: Date Completed : 9/3/2024 2:42:36 PM The structural review is approved. Subject to the field inspector’s approval. Building(B) Reviewer Keith Miller kmiller@safebuilt.com Denied Reason: Date Completed : 9/3/2024 2:39:48 PM 1. Sheet C1.0: Specify if a fire alarm system is being installed. (2018 IBC section 107) Mechanical(M) Reviewer Keith Miller kmiller@safebuilt.com Denied Reason: Date Completed : 9/3/2024 2:41:17 PM 1. General: Provide the mechanical scope of work, equipment schedule, plans, details showing compliance with the 2018 IECC section C403. (2018 IBC section 107) Electrical(E) Reviewer Keith Miller kmiller@safebuilt.com Denied Reason: Date Completed : 9/3/2024 2:40:39 PM 1. Sheet E1.0: Identify all GFCI protected receptacles. (2017 NEC section 210.8) 2. Sheet E1.0: The lavatory receptacle is shown as 220v which should likely be 120v. Please verify and correct the note. (2018 IBC section 107) 3. Sheet E1.0: Specify that the toilet room fan exhausts to the exterior. (2018 IMC sections 403.2.1, 501.3) Plumbing(P) Reviewer Keith Miller kmiller@safebuilt.com Denied Reason: Date Completed : 9/3/2024 2:41:45 PM 1. Sheet P1.0: Include the faucet specifications showing compliance with the automatic faucets details in the 2018 IPC amended sections 412.11, 419.6. 2. Sheet P1.0: Provide the gas piping sizing diagram and calculations. (2018 IFGC section 402) |
||
| 09/19/2024 | Fire New Construction | REQUIRES RESUBMIT | -List the height of storage. If the height of storage is over 12', it is considered high piled storage and additional information will be required per IFC Ch. 32. john.vincent@tucsonaz.gov 5203495581 |
||
| 09/23/2024 | Site Engineering | REQUIRES RESUBMIT | 1. The associated development package TD-DEV-0524-00149 must be approved before this building permit can be approved. 2. A floodplain use permit with elevation certificate is required and must be issued before this building permit can be approved. This floodplain use permit can also include the grading associated with TD-DEV-0524-00149. Include the plan set showing the FFE of the building and the grading sheets for the floodplain use permit submittal. Mike Ortiz michael.ortiz@tucsonaz.gov |
||
| 09/18/2024 | Site Zoning | REQUIRES RESUBMIT | FROM: PDSD Zoning Review Section PROJECT: TC-COM-0824-01636 - TD-DEV-0524-00149 117 E FORT LOWELL RD. - C-2 Commercial Storage (1st Review) TRANSMITTAL DATE: September 18, 2024 COMMENTS: Resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This site is located in the C-2 zone (UDC 4.7.21). Commercial Storage use is a permitted use in the zone (UDC Table 4.8-4), subject to Use Specific Standard 4.9.10.A. 1. Zoning has reviewed the building permit for compliance with development package TD-DEV-0524-00149 and although it appears that the building plan is in compliance until the DP is approved by all review agencies Zoning cannot approve this plan. If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov. |
||
| 09/19/2024 | Water - PDSD | REQUIRES RESUBMIT | Show the location of the reduced pressure backflow assembly on the drawings; indicate the size of the assembly. Reference: Chapter XXVII, Article V, Section 27-72, the Tucson Code, https://www.tucsonaz.gov/files/sharedassets/public/city-services/tucson-water/water-quality/documents/backflow-ordinance.pdf. | ||
| 08/22/2024 | PDSD Application Completeness Express | REVIEW COMPLETED |