Permit Number: TC-COM-0824-01624
Parcel: 12112001B

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.2

Permit Number - TC-COM-0824-01624
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
10/14/2024 Bldg Permits - Post Review PENDING ASSIGNMENT
10/14/2024 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Structural(S) Reviewer
Madeline Nelson
mnelson@safebuilt.com
Approved
Reason:
Date Completed : 10/9/2024 9:53:22 PM





Building(B) Reviewer (from previous submittal TUC9592001.082124)
Kimiyoshi Shimabukuro
kshimabukuro@safebuilt.com
Approved
Reason:
Date Completed : 8/24/2024 10:28:56 PM






Mechanical(M) Reviewer
Jorge Valido
jvalido@safebuilt.com
Denied
Reason:
Date Completed : 10/11/2024 10:07:05 AM
1. (UNRESOLVED) - General - Provide Heat Load calculations. Include O/A in the Calculations. - 2015 IECC Section C403.2.1 Calculation of heating and cooling loads.
i. COMcheck for RTU-1 shows 102 (MBH) Heat Load Calculations show 58 (MBH). Confirm Heat Load Calculations. - 2018 IECC - C403.3.1 Equipment sizing (Mandatory).
2. (RESOLVED) - Plan Sheet M0.02 - Provide on the RTU Schedule Total BTUH, Sensible BTUH, and Latent BTUH. Al values must meet COMcheck Mechanical Compliance Certificate submitted and Heat Load Calculations. - 2015 IECC
Section C103.2Information on construction documents - 2018 IBC – Section [A]107.2.1Information on construction documents.
3. (RESOLVED) - Plan Sheet M2.02 - If applicable. Provide clear dimensions from all serviceable equipment to the edge
of building on roof. (RTU #3, DSCU 1, DSCU-2) - 2018 IMC Section [BE] 304.11 Guards.





Electrical(E) Reviewer (from previous submittal TUC9592001.082124)
Ron Ross
rross@safebuilt.com
Approved
Reason:
Date Completed : 8/29/2024 10:32:56 AM





Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Approved
Reason:
Date Completed : 10/13/2024 5:54:08 PM
Second Plumbing Review: OK
Resolved_1). PLAN PAGE P3.01: Drinking fountain symbol in wrong location on both riser diagrams. Correctly Identify the
Drinking fountain location. -2018 IPC 106.3.1
10/04/2024 PDSD Application Completeness REVIEW COMPLETED