Permit Number: TC-COM-0824-01568
Parcel: 10610005D

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.2

Permit Number - TC-COM-0824-01568
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
12/10/2024 Bldg Permits - Post Review PENDING ASSIGNMENT
11/25/2024 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Structural(S) Reviewer (from previous submittal TUC9588001.081424)
Madeline Nelson
mnelson@safebuilt.com
Approved
Reason:
Date Completed : 8/27/2024 10:31:16 PM




Building(B) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 11/21/2024 11:19:07 AM
1. Unresolved - General: Include the window and door schedules specifying the U-Factors. (2018 IBC section 107, 2018
IECC section C402) The warehouse area is shown as being conditioned space with 6 new RTU’s and requires compliance with the provisions of the 2018 IECC. The removal of the exiting envelope retail storefront and the installation of new walls, roof, and doors creates a new envelope.
2. Resolved - Sheet X1: Include the uses of the adjacent spaces and required rated separation details per 2018 IBC Table 508.4 as applicable.
3. Resolved - Sheet X1.1: Specify if fire alarms are installed. (2018 IBC section 107)
4. Resolved - Sheet A7: The Keynote marks do not correspond to the building section details. Please coordinate and correct notes and all affected details. (2018 IBC section 107)
5. Unresolved - Sheet A7: Include the envelope insulation details meeting the requirements of the 2018 IECC section C402. The warehouse area is shown as being conditioned space with 6new RTU’s and requires compliance with the
provisions of the 2018 IECC. The removal of the exiting envelope retail storefront and the installation of new walls, roof, and doors creates a new envelope.
6. Unresolved – General: A Special Inspections Intermediate Certificate needs to be submitted with parts A & B completed for verification of the approved Special Inspectors for the special inspections required. (2018 IBC section
1704.2.1, Required Tucson submittal requirements.)





Mechanical(M) Reviewer
Jorge Valido
jvalido@safebuilt.com
Approved with Comments
Reason:
Date Completed : 11/20/2024 9:17:23 AM
1. (RESOLVED) - General - Provide COMcheck Mechanical Compliance Certificate. Any other APPROVED certifying agency can be used. - 2018 IECC Section C403.3.2 HVAC equipment performance requirements.
2. (RESOLVED) - General - Provide Heat load calculations - 2018 IECC Section C403.1.1 Calculation of heating and cooling loads
3. (RESOLVED) - General - Provide Specifications/Schedule for the existing RTU. - 2018 IECC Section C103.2Information on construction documents - 2018 IBC – Section [A]107.2.1Information on construction documents.
ALL FUTURE A/C NOTED ON PLANS WILL REQUIRE NEW PERMIT AND NEW REVIEW.






Electrical(E) Reviewer (from previous submittal TUC9588001.081424)
Ron Ross
rross@safebuilt.com
Approved
Reason:
Date Completed : 8/17/2024 12:12:15 PM





Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Approved with Comments
Reason:
Date Completed : 11/24/2024 10:07:56 PM
Second Plumbing Review:ok subject to field inspections
Resolved-1). Plan Page P1: plan set missing development package for trench drain piping & continuation of sump piping as stated. Provide develop package for trench drain piping & continuation of sump piping to termination, as stated. -2018 IPC
106.3.1
Resolved-2). Plan Page P1: missing sump tank vent. Add sump tank vent. -2018 IPC 712.3.2 ok subject to field inspections-3). Plan Page P1: Sump pump discharge piping needs check valve and shut off valve. Add a
detail showing Sump pump discharge piping check valve and shut off valve. -2018 IPC 712.2 **note not found as stated in response comments**
Resolved-4). Plan page A5: Missing downspout & gutter locations. Add the 5 downspouts & gutter illustrations to the plan page. -2018 IPC 106.3.1
Resolved-5). Plan page A5: Plan page A5 states discharge roof downspouts to exterior trench drain. Provide develop package for trench drain piping & continuation of sump piping to termination to determine what system this exterior trench
drain discharges to. -2018 IPC 1101.3
12/03/2024 Fire New Construction REQUIRES RESUBMIT Correct listed max travel distance on Exit Plan (sheet X1.1). Maximum travel distance is listed as 407'-2".
Questions: sal.erivezjr@tucsonaz.gov
12/04/2024 Site Engineering REQUIRES RESUBMIT TC-COM-0824-01568
2020 W PRINCE RD

Site engineering comments are as follows:
1. TC-COM-0824-01568 cannot be approved before TD-DEV-0724-00210 is approved by all reviewers. UDC Article 3.3.3.7.a
Ryan Insalaco - ryan.insalaco@tucsonaz.gov
12/10/2024 Site Zoning REQUIRES RESUBMIT ZONING REVIEW TRANSMITTAL
FROM: PDSD Zoning Review

PROJECT: TC-COM-0824-01568
2020 W PRINCE RD Unit: 150 (I-1)
Demolition of showroom and addition of warehouse in reduced footprint (2nd Review)

TRANSMITTAL: December 10, 2024

This site is located in I-1 Zone (UDC 4.7.29), Commercial Storage use is an allowed use in the zone (UDC Table 4.8-5) subject to Use Specific Standards 4.9.10.A and 4.9.13.Q.

1. Comment: As of 12/10/24, the development package (TD-DEV-0724-00210) has not been approved. Site zoning has done a cursory review of the building plans. At this time, zoning cannot approve the building plans until the DP is approved and in compliance with the approved DP.
2. Comment: Zoning will review the building plans on the next submittal to verify compliance with the approved development package. Please ensure the site plan in the building permit matches the site plan from the approved development package.
3. Comment: Please reference the DP and demo case numbers next to the title block associated with this project (TD-DEV-0724-00210 and TC-DMO-0824-00180).
4. Comment: Please remove and do not include bubble clouds on corrections made to the current building plan documents under review. (Revision clouds should only be included on approved plans that are in for a revision.)
5. Comment: Please include a comment response narrative stating how all zoning review comments have been addressed.

If you have any questions about this review, please contact Bobby Parsons at Robert.Parsons@tucsonaz.gov.
11/19/2024 PDSD Application Completeness REVIEW COMPLETED