Permit Number: TC-COM-0823-01968
Parcel: 12101103H

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0823-01968
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
12/19/2023 Bldg Permits - Post Review PENDING ASSIGNMENT
12/19/2023 Commercial Plumbing REQUIRES RESUBMIT 1. Install the sump pump with a 1-1/2” diameter discharge pipe per the manufacturer’s instructions. Connect to the 2” horizontal drainage piping above the ceiling as described in Section 712.3.5, IPC 2018. Reference: Section 303.2, IPC 2018.
2. SDR 35 PVC pipe is not approved for use within a building or above ground (you can use schedule 40 PVC, see Table 702.1, IPC 2018). Reference: Section 702.1, IPC 2018.
3. Based on a flow of 5 GPM, the horizontal drainage piping shall have a minimum slope of ¼” per foot. Reference: Section 709.3 and Table 710.1, IPC 2018.
4. Show the installation of a check valve and a full open valve on the discharge from the sump pump. The valves shall be accessible. Reference: Section 712.2, IPC 2018.
11/29/2023 PDSD Application Completeness REVIEW COMPLETED