Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0823-01958
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/16/2023 | Site Zoning | APPROVED | |||
| 09/13/2023 | Water - PDSD | APPROVED | |||
| 08/13/2023 | Fire New Construction | NOT REQUIRED | |||
| 08/17/2023 | Site Engineering | NOT REQUIRED | |||
| 09/13/2023 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 08/17/2023 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Structural(S) Reviewer Keith Miller kmiller@safebuilt.com Denied Reason: Date Completed : 8/17/2023 12:09:28 PM See the building review comments. Building(B) Reviewer Keith Miller kmiller@safebuilt.com Denied Reason: Date Completed : 8/17/2023 12:04:11 PM 1) Sheet A0.0 (Cover Sheet): Include the allowed vs actual area, height, and number of stories. (2018 IBC Chapter 5) 2) Sheet P1.1 (Underground Plumbing Drawings): The underground sewer and water main piping are shown under the building support piers shown on sheet #9. The piping depth is not detailed. Please revise the plans based on the final foundation plans to be submitted. (2018 IPC section 305) 3) Sheet #7 (Elevation Views): An accessible building entrance and steps are not shown on the elevation views. Please revise all affected sheets. (2018 IBC sections 1106, 1011, 1012, 1014) 4) Sheet #9 (Foundation Drawing): The foundation pier drawing is noted that it is for reference only and a separate site specific installation plan is required. Please submit a geotechnical engineer report and foundation plans including the anchoring/tie-down drawings. (2018 IBC sections 107, 1803) Mechanical N/A Electrical(E) Reviewer Keith Miller kmiller@safebuilt.com Denied Reason: Date Completed : 8/17/2023 12:08:40 PM See the building review comments. Plumbing(P) Reviewer Keith Miller kmiller@safebuilt.com Denied Reason: Date Completed : 8/17/2023 12:09:09 PM See the building review comments. |
||
| 08/11/2023 | PDSD Application Completeness Express | REVIEW COMPLETED |