Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0823-01889
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 02/11/2025 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 02/11/2025 | Commercial Building Standard | REQUIRES RESUBMIT | February 10, 2025 3rd Review Centennial American Properties Attn: Jason Tankersley 1200 East Morehead, Suite 280 Charlotte, North Carolina 28204 Re: CAP STORAGE – GOLF LINKS NEW BUILDING (REVISIONS) City of Tucson Permit Number: TC-COM-0823-01889 Stantec Project Number: 185215066 Stantec File Number: TUC-24-109 Plan review for the above referenced project has been completed. This letter reflects comments to be addressed. PLEASE send all response to comments back to the City through the permit portal! Responses sent directly to Stantec will be ignored. Also, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. Please cloud and delta all changes and provide a letter with a written response to each of the comments indicating the action taken. The scope of this review covers the architectural, structural, plumbing, mechanical, and electrical designs as they relate to the codes adopted by the jurisdiction. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions, and concerns before permit approval. Occupancy Group Construction Type Area (Square feet) Occupant Load Automatic Fire Sprinklers Fire Alarms S-1 II-B 103,604 220 Yes No Separate Permits: Automatic fire sprinklers and signage. Deferred Submittals: Metal stairs, storefront and window system, elevator shop drawings, prefabricated canopy Special Inspections: Earthwork, concrete, epoxy and expansion anchors, structural steel, high-strength bolts, field welding, and masonry. ARCHITECTURAL COMMENTS General 1. New Comment: One of the primary changes to this project was to add an elevator equipment room, and the drawings have been revised to show this room. Further the room is shown as being separated from the rest of the facility with a 1-hour fire barrier. Please indicate that the elevator machinery room walls AND the floor ceiling assembly that separates this room from the rest of the facility are separated with a 1-hour horizontal assembly as required by 2018 IBC Sec. 3005.4, and further provide on the plans a detail and the listing information for this horizontal assembly. Sheet A001 1. Addressed. 2. Addressed. 3. Addressed. Sheet A002 1. Addressed. Sheet A100 1. Addressed. 2. Addressed. Sheet A102.1 1. Addressed. Sheet A122 1. Addressed. Sheet A131 1. Addressed. Sheet A500 1. Addressed. Sheet A920 1. Addressed. STRUCTURAL COMMENTS General 1. Addressed. 2. Addressed. Sheet S120 1. Addressed. Sheet S501 1. Addressed. MECHANICAL COMMENTS There are no comments. PLUMBING COMMENTS Sheet P101 1. Addressed. 2. Addressed. 3. Addressed. ELECTRICAL COMMENTS General 1. Addressed. 2. Addressed. 3. Addressed. Should you have any questions regarding the plan review comments, please contact the plan reviewer listed for the appropriate discipline. Plans reviewed by: Trevor Bies, Senior Plan Reviewer 602-338-9922 trevor.bies@stantec.com |
||
| 02/11/2025 | Commercial Plumbing Standard | REQUIRES RESUBMIT | February 10, 2025 3rd Review Centennial American Properties Attn: Jason Tankersley 1200 East Morehead, Suite 280 Charlotte, North Carolina 28204 Re: CAP STORAGE – GOLF LINKS NEW BUILDING (REVISIONS) City of Tucson Permit Number: TC-COM-0823-01889 Stantec Project Number: 185215066 Stantec File Number: TUC-24-109 Plan review for the above referenced project has been completed. This letter reflects comments to be addressed. PLEASE send all response to comments back to the City through the permit portal! Responses sent directly to Stantec will be ignored. Also, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. Please cloud and delta all changes and provide a letter with a written response to each of the comments indicating the action taken. The scope of this review covers the architectural, structural, plumbing, mechanical, and electrical designs as they relate to the codes adopted by the jurisdiction. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions, and concerns before permit approval. Occupancy Group Construction Type Area (Square feet) Occupant Load Automatic Fire Sprinklers Fire Alarms S-1 II-B 103,604 220 Yes No Separate Permits: Automatic fire sprinklers and signage. Deferred Submittals: Metal stairs, storefront and window system, elevator shop drawings, prefabricated canopy Special Inspections: Earthwork, concrete, epoxy and expansion anchors, structural steel, high-strength bolts, field welding, and masonry. ARCHITECTURAL COMMENTS General 1. New Comment: One of the primary changes to this project was to add an elevator equipment room, and the drawings have been revised to show this room. Further the room is shown as being separated from the rest of the facility with a 1-hour fire barrier. Please indicate that the elevator machinery room walls AND the floor ceiling assembly that separates this room from the rest of the facility are separated with a 1-hour horizontal assembly as required by 2018 IBC Sec. 3005.4, and further provide on the plans a detail and the listing information for this horizontal assembly. Sheet A001 1. Addressed. 2. Addressed. 3. Addressed. Sheet A002 1. Addressed. Sheet A100 1. Addressed. 2. Addressed. Sheet A102.1 1. Addressed. Sheet A122 1. Addressed. Sheet A131 1. Addressed. Sheet A500 1. Addressed. Sheet A920 1. Addressed. STRUCTURAL COMMENTS General 1. Addressed. 2. Addressed. Sheet S120 1. Addressed. Sheet S501 1. Addressed. MECHANICAL COMMENTS There are no comments. PLUMBING COMMENTS Sheet P101 1. Addressed. 2. Addressed. 3. Addressed. ELECTRICAL COMMENTS General 1. Addressed. 2. Addressed. 3. Addressed. Should you have any questions regarding the plan review comments, please contact the plan reviewer listed for the appropriate discipline. Plans reviewed by: Trevor Bies, Senior Plan Reviewer 602-338-9922 trevor.bies@stantec.com |
||
| 02/06/2025 | PDSD Application Completeness Express | REVIEW COMPLETED |