Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0726-01197
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/21/2026 | Site Engineering Standard | APPROVED | |||
| 08/20/2026 | Site Zoning Standard | APPROVED | |||
| 09/28/2026 | Commercial Electrical Standard | NOT REQUIRED | |||
| 09/28/2026 | Commercial Mechanical Standard | NOT REQUIRED | |||
| 08/21/2026 | Fire New Construction Standard | NOT REQUIRED | |||
| 08/17/2026 | Outdoor Lighting Standard | NOT REQUIRED | No modifications to the outdoor lighting. | ||
| 08/21/2026 | Site Landscape Standard | NOT REQUIRED | |||
| 08/21/2026 | Water - PDSD Standard | NOT REQUIRED | |||
| 09/28/2026 | Commercial Post Review Express | PENDING ASSIGNMENT | |||
| 09/28/2026 | Commercial Building Standard | REQUIRES RESUBMIT | August 13, 2026 1st Review Southwest Value Partners Attn: David Miller 12770 El Camino Real, Suite 200 San Diego, California 92130 Re: STARR PASS FIREPITS ADDITION City of Tucson Permit Number: TC-COM-0726-01197 Stantec Project Number: 185215066 Stantec File Number: TUC-26-045 Plan review for the project referenced above has been completed. This letter reflects comments to be addressed. PLEASE send all responses to comments back to the City through the permit portal! Responses sent directly to Stantec will be ignored. Also, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. Please cloud and delta all changes and provide a letter with a written response to each of the comments indicating the action taken. The scope of this review covers the architectural, structural, and plumbing designs as they relate to the codes adopted by the jurisdiction. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions, and concerns before permit approval. Occupancy Group Construction Type Area (Square feet) Occupant Load Automatic Fire Sprinklers Fire Alarms N/A N/A 4,486 N/A N/A N/A Separate Permits: None. Deferred Submittals: None. Special Inspections: None. ARCHITECTURAL COMMENTS Sheet A0 1. General Requirements: Demolition is mentioned; however no demolition plan is included; Please clarify the extent of demolition needed. Sheets A2.0 and A2.1 1. Some, or all the patio extensions appear to be below adjacent grade; please clarify what provisions have been made for drainage of rainwater at these locations. Sheet A3.0 1. Detail 5: There appears to be a typo on the footing width shown; please clarify. {Is the footing really 53’-4” wide?} STRUCTURAL COMMENTS Sheet A3.0 1. Detail 5: The masonry walls are retaining as much as 40” of earth. Where are the structural calculations to justify vertical reinforcement spacing for this retainage? PLUMBING COMMENTS There were no comments. Should you have any questions regarding the plan review comments, please contact the plan reviewer listed for the appropriate discipline. Plans reviewed by: Robert Chandler Senior Building Inspector 520-565-0181 robert.chandler2@stantec.com |
||
| 09/28/2026 | Commercial Plumbing Standard | REQUIRES RESUBMIT | August 13, 2026 1st Review Southwest Value Partners Attn: David Miller 12770 El Camino Real, Suite 200 San Diego, California 92130 Re: STARR PASS FIREPITS ADDITION City of Tucson Permit Number: TC-COM-0726-01197 Stantec Project Number: 185215066 Stantec File Number: TUC-26-045 Plan review for the project referenced above has been completed. This letter reflects comments to be addressed. PLEASE send all responses to comments back to the City through the permit portal! Responses sent directly to Stantec will be ignored. Also, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. Please cloud and delta all changes and provide a letter with a written response to each of the comments indicating the action taken. The scope of this review covers the architectural, structural, and plumbing designs as they relate to the codes adopted by the jurisdiction. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions, and concerns before permit approval. Occupancy Group Construction Type Area (Square feet) Occupant Load Automatic Fire Sprinklers Fire Alarms N/A N/A 4,486 N/A N/A N/A Separate Permits: None. Deferred Submittals: None. Special Inspections: None. ARCHITECTURAL COMMENTS Sheet A0 1. General Requirements: Demolition is mentioned; however no demolition plan is included; Please clarify the extent of demolition needed. Sheets A2.0 and A2.1 1. Some, or all the patio extensions appear to be below adjacent grade; please clarify what provisions have been made for drainage of rainwater at these locations. Sheet A3.0 1. Detail 5: There appears to be a typo on the footing width shown; please clarify. {Is the footing really 53’-4” wide?} STRUCTURAL COMMENTS Sheet A3.0 1. Detail 5: The masonry walls are retaining as much as 40” of earth. Where are the structural calculations to justify vertical reinforcement spacing for this retainage? PLUMBING COMMENTS There were no comments. Should you have any questions regarding the plan review comments, please contact the plan reviewer listed for the appropriate discipline. Plans reviewed by: Robert Chandler Senior Building Inspector 520-565-0181 robert.chandler2@stantec.com |
||
| 07/31/2026 | PDSD Application Completeness Express | REVIEW COMPLETED |