Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Number: TC-COM-0726-01007
Parcel: 133231420

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - LIMITED v.1

Permit Number - TC-COM-0726-01007
Review Name: COMMERCIAL REVIEW - LIMITED v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
07/17/2026 Commercial Building APPROVED
07/16/2026 Commercial Electrical APPROVED
07/15/2026 Site Zoning APPROVED
07/17/2026 Water - PDSD APPROVED
07/10/2026 Site Engineering NOT REQUIRED
07/17/2026 Bldg Permits - Post Review Express PENDING ASSIGNMENT
07/17/2026 Commercial Mechanical REQUIRES RESUBMIT ACTIVITY NO. TC-COM-0726-01007
ADDRESS/PARCEL: 7725 E BROADWAY BL TUCSON, AZ 85710

Submit your revised drawings along with a detailed response letter, which states how all comments were addressed. Review will not proceed without the response letter. The submitted documents were incomplete and a thorough plan review could not be performed. Please be aware, new comments may arise with the next review.

If you have any questions about these review comments, I can be reached at Sean.Severson@tucsonaz.gov

COMMENTS:

1. Please provide ventilation calculations demonstrating compliance with the minimum outdoor air and exhaust ventilation requirements. Reference: Section 1008.1, IEBC 2024 & Table 403.3.1.1, IMC 2024.
07/17/2026 Commercial Plumbing REQUIRES RESUBMIT ACTIVITY NO. TC-COM-0726-01007
ADDRESS/PARCEL: 7725 E BROADWAY BL TUCSON, AZ 85710

Submit your revised drawings along with a detailed response letter, which states how all comments were addressed. Review will not proceed without the response letter. The submitted documents were incomplete and a thorough plan review could not be performed. Please be aware, new comments may arise with the next review.

If you have any questions about these review comments, I can be reached at Sean.Severson@tucsonaz.gov

COMMENTS:

1. Please verify that the distance from the hot water source to the hot water termination for the lavatory complies with the requirements of Section C404.5, IECC 2024 (e.g., 24” for ½” hot water supply piping).
2. Please specify a metering faucet for the lavatory, dispensing a maximum of 0.25 gallons per metering cycle. Verify that the faucet cycle will last for at least 10 seconds. Reference: Section 412.13, IPC 2024, as amended by the City of Tucson and Section 606.4, ICC/ANSI A117.1-09.
3. Provide a detail of the water heater installation above the mop sink, including the method of support, excess pressure relief, expansion tank, vacuum relief or other anti-siphon device, safety pan, and valves. Reference: Sections 503.1 [connections & SOV], 504 [Safety devices], 606.1 [valves], 607.2 [recirculation], and 607.3 [thermal expansion control], IPC 2024.
07/17/2026 Fire New Construction REVIEW COMPLETED
07/02/2026 PDSD Application Completeness Express REVIEW COMPLETED