Permit Number: TC-COM-0725-01323
Parcel: 10913008B

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0725-01323
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
08/01/2025 Site Engineering Standard APPROVED
08/07/2025 Outdoor Lighting Standard NOT REQUIRED No modifications to the outdoor lighting.
08/11/2025 Site Zoning Standard NOT REQUIRED
08/14/2025 Bldg Permits - Post Review Express PENDING ASSIGNMENT
08/14/2025 Commercial Building Standard REQUIRES RESUBMIT Please submit your revised documents and provide a letter with a written response letter addressing each of the comments indicating how the Review comments were resolved. Additionally, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. Please note the submittal was incomplete and the plan review was conducted using the information presented. The subsequent review could generate more comments after original comments have been addressed.
1. Please amend Sheet S-000 Structural Cover sheet to remove “Preliminary” from the sheet. IBC 107.2.1
Please contact me if you have any questions about these comments.
Mark Masek
Plans Examiner – Building Safety
Planning and Development Services | City of Tucson
main 520.837.4994
email mark.masek@tucsonaz.gov
08/07/2025 Commercial Electrical Standard REQUIRES RESUBMIT Commercial Electrical Review TC-COM-0725-01323 (5300 N VALLEY VIEW RD TUCSON, AZ 85718)
Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. Provide updated Plans/calculations and a written response Letter to each of the notated items indicating action taken. Resubmitted plans that do not contain a written response Letter addressing each of the notated items indicating action taken, may be delayed until response letter is received.
Code reference, 2018 International Building Code (IBC), 2017 National Electrical Code (NEC).


1. Show PV interconnection in compliance with NEC 705.32. Reference also NEC 230.95
705.32 Ground-Fault Protection.

Contact Jeremy Hamblin with any questions: Jeremy.hamblin@tucsonaz.gov
07/25/2025 Fire New Construction Standard REVIEW COMPLETED
07/22/2025 PDSD Application Completeness Express REVIEW COMPLETED