Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0725-01323
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/01/2025 | Site Engineering Standard | APPROVED | |||
| 08/07/2025 | Outdoor Lighting Standard | NOT REQUIRED | No modifications to the outdoor lighting. | ||
| 08/11/2025 | Site Zoning Standard | NOT REQUIRED | |||
| 08/14/2025 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 08/14/2025 | Commercial Building Standard | REQUIRES RESUBMIT | Please submit your revised documents and provide a letter with a written response letter addressing each of the comments indicating how the Review comments were resolved. Additionally, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. Please note the submittal was incomplete and the plan review was conducted using the information presented. The subsequent review could generate more comments after original comments have been addressed. 1. Please amend Sheet S-000 Structural Cover sheet to remove “Preliminary” from the sheet. IBC 107.2.1 Please contact me if you have any questions about these comments. Mark Masek Plans Examiner – Building Safety Planning and Development Services | City of Tucson main 520.837.4994 email mark.masek@tucsonaz.gov |
||
| 08/07/2025 | Commercial Electrical Standard | REQUIRES RESUBMIT | Commercial Electrical Review TC-COM-0725-01323 (5300 N VALLEY VIEW RD TUCSON, AZ 85718) Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. Provide updated Plans/calculations and a written response Letter to each of the notated items indicating action taken. Resubmitted plans that do not contain a written response Letter addressing each of the notated items indicating action taken, may be delayed until response letter is received. Code reference, 2018 International Building Code (IBC), 2017 National Electrical Code (NEC). 1. Show PV interconnection in compliance with NEC 705.32. Reference also NEC 230.95 705.32 Ground-Fault Protection. Contact Jeremy Hamblin with any questions: Jeremy.hamblin@tucsonaz.gov |
||
| 07/25/2025 | Fire New Construction Standard | REVIEW COMPLETED | |||
| 07/22/2025 | PDSD Application Completeness Express | REVIEW COMPLETED |