Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0724-01382
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
08/14/2024 Site Zoning APPROVED
08/19/2024 Water - PDSD APPROVED
08/19/2024 Site Engineering NOT REQUIRED
08/19/2024 Bldg Permits - Post Review Express PENDING ASSIGNMENT
08/02/2024 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Building(B) Reviewer
Janet Matz
jmatz@safebuilt.com
Denied
Reason:
Date Completed : 8/2/2024 5:52:32 AM
All corrections must be clouded, delta numbered, with a brief explanation within the plan sheet or the title block of the sheet. Please include with the resubmittal a separate response narrative, which is numbered or itemized to correspond to each of
the noted plan review comments items.
1. (General) Please update the title blocks of all sheets to include the date signed by the Architect of record on the seal.
2. Sheet A1.1 (Life Safety Plan). Note on the drawings that that all alterations shall be done in a manner that maintains the level of fire protection (2018 IEBC Sec. 703.1).
3. Sheet A1.1 (Life Safety Plan). Clarify that the exit door shown to the right of the proposed recruiting asst. area has enough door clearance to be considered an exit. The angled wall appears to cut the clearance in such a way that the minimum width may not be possible. Show the minimum accessible floor clearance on the plans. (ICC A117.1- 2009 Figure 404.2.3.2).
4. Sheet A2.0 (Floor Plan). The Floor plan Key Note 11 indicates a 12” raised platform for the command center area. Provide construction details for this platform and provide information on the step up or ramp that will be needed.
5. Sheet A3.0 (Reflected Ceiling Plan). The RCP general notes indicate a security system will be installed by the tenant. Clarify if this will be part of this permit or if a separate permit will be submitted. IF the low voltage work is part of this permit, provide details for its installation on the electrical plans.
6. Sheet A4.0 (Finish Schedule). Indicate on the Room Finish Schedule that all interior finishes will be in accordance with 2018 IBC Sec. 803.1.





Electrical(E) Reviewer
Janet Matz
jmatz@safebuilt.com
Denied
Reason:
Date Completed : 8/2/2024 5:53:34 AM
1. Sheet E2.1 (Lighting Plan). Indicate the location of all “night lighting” on the plans for egress illumination or indicate light sensors will be used. All rooms and usable floor surfaces in a building shall be equipped with artificial lighting and
shall be illuminated at all times that the space is occupied. (2018 IBC Section 1008.2).
2. Sheet E2.1 (Lighting Plan). Indicate additional EM lighting (headlamps or other type) in the renovated Reception/ Waiting Area and by the new Collab Area where the walls were modified. Verify that the corridor outside of Offices 301, 302 and 303 has sufficient EM lighting and if not add an additional fixture in this location. (2018 IBC Section 1008.3).
3. Sheet E2.1 (Lighting Plan). Verify that the exit lighting is still sufficient after the wall modifications, it appears that the Collab Area may no longer make sense. Modify as needed. (2018 IBC Section 1013.1).
4. Sheet E2.1 (Lighting Plan). Indicate the lighting will be controlled by occupancy sensors. Occupancy sensors are required for all areas that were modified as part of the renovation. (2018 IECC C405.2.1 and C503.6).
08/16/2024 Fire New Construction REQUIRES RESUBMIT Address SAFEbuilt comments.
Questions: patricia.shelton@tucsonaz.gov
07/18/2024 PDSD Application Completeness Express REVIEW COMPLETED