Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.2
Permit Number - TC-COM-0724-01379
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 10/07/2024 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 09/11/2024 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Structural(S) Reviewer Janet Matz jmatz@safebuilt.com Denied Reason: Date Completed : 9/10/2024 11:53:54 PM Revised plans to do not clearly indicate the location of the corrections on the drawings. Please cloud and delta number all corrections on the drawings for review, and indicate the revision number and note in the title block of each sheet that was modified. 1. Sheet 1 Site Plan- Indicate with the general information and zoning information that the wood truss drawings will be a differed submittal or provide full drawings and calculations for the tusses. Comment not addressed, note not found. Building(B) Reviewer Janet Matz jmatz@safebuilt.com Denied Reason: Date Completed : 9/10/2024 11:40:20 PM All corrections must be clouded, delta numbered, with a brief explanation within the plan sheet or the title block. Please include with the resubmittal a separate response narrative, which is numbered or itemized to correspond to each of the noted plan review comments items. Revised plans to do not clearly indicate the location of the corrections on the drawings. Please cloud and delta number all corrections on the drawings for review, and indicate the revision number and note in the title block of each sheet that was modified. Mechanical(M) Reviewer Janet Matz jmatz@safebuilt.com Denied Reason: Date Completed : 9/10/2024 11:47:22 PM Revised plans to do not clearly indicate the location of the corrections on the drawings. Please cloud and delta number all corrections on the drawings for review, and indicate the revision number and note in the title block of each sheet that was modified. 1. Sheet 10 Mechanical- Provide a Mechanical RES-Check or Manual J/S/D calculations for the new forced air units to verify the proper sizing. (2018 IECC Section R403.7). Comment not addressed. If this information is to be provided as a deferred submittal, note it as such on the drawings. 2. Sheet 10 Mechanical- Note on the drawings that a duct leakage test will be preformed by a third party and provided to the code official unless al of the ductwork is within conditioned space. (2018 IECC R403.3.4). Comment addressed. 3. Sheet 10 Mechanical- Note on the drawings that a programable thermostat will be provided for the primary system capable of controlling the system on a daily schedule. (2018 IECC R403.1). Comment addressed. Electrical(E) Reviewer Janet Matz jmatz@safebuilt.com Denied Reason: Date Completed : 9/10/2024 11:42:47 PM Revised plans to do not clearly indicate the location of the corrections on the drawings. Please cloud and delta number all corrections on the drawings for review, and indicate the revision number and note in the title block of each sheet that was modified. 1. Sheet 12 Electrical Power Plan- Provide an additional countertop receptacle in the kitchen in the corner between the stove and sink, it appears that the spacing exceeds the maximum. (2017 NEC 210.52 (3)). Comment Adressed. 2. Sheet 13 Electrical Notes- Update the electrical notes to reference the 2017 NEC not the 2002. Comment not addressed 3. Sheet 13 Electrical Notes- Note on the drawings that all 15 and 20 amp nonlocking receptacles shall be tamper resistant receptacles. (2017 NEC 406.12). Comment Addressed. Plumbing(P) Reviewer Janet Matz jmatz@safebuilt.com Denied Reason: Date Completed : 9/10/2024 11:51:42 PM Revised plans to do not clearly indicate the location of the corrections on the drawings. Please cloud and delta number all corrections on the drawings for review, and indicate the revision number and note in the title block of each sheet that was modified. 1. Sheet 9 Plumbing Plan- Note on the drawings that a galvanized steel pan will be required under the second floor storage type tank water heaters. (2018 IPC Section 504.7). Comment not addressed. 2. Sheet 9 Plumbing Plan- Note on the drawings that all hot water piping will be insulated to a minimum of R3 if using the prescriptive method of compliance. (2018 IECC R403.5.3). Comment addressed. |
||
| 10/07/2024 | Site Engineering | REQUIRES RESUBMIT | 1. Please see Zoning comments. Per UDC Article 3.3.3.G.2.c A site plan (Development Package) is required for the following types of development: Existing development undergoing a change of use, building structure additions, and/or a reconfiguration of an area outside a building. | ||
| 10/03/2024 | Site Zoning | REQUIRES RESUBMIT | FROM: PDSD Zoning Review Section PROJECT: TC-COM-0724-01379 106 W DELANO ST. – O-3 Multifamily (2nd Review) TRANSMITTAL DATE: October 3, 2024 Resubmit revised drawings with a detailed response letter stating how all Zoning Review Section comments were addressed. 1. This comment was not addressed. The required DP is a separate submittal and shall be approved by all review agencies prior to approval of this building plan. Per UDC Article 3.3.3.G.2.c A site plan (Development Package) is required for the following types of development: Existing development undergoing a change of use, building structure additions, and/or a reconfiguration of an area outside a building. A development package (DP) meeting the requirements of Administrative Manual (AM) 2-06 must be submitted and approved prior to approval of this building plan. The Administrative Manual can be found at: https://www.tucsonaz.gov/Departments/Planning-Development-Services/Codes-and-Plans/Zoning-Code#section-1. If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov. |
||
| 10/01/2024 | Water - PDSD | REQUIRES RESUBMIT | Provide the size of the water meter and the size of the water service pipe to the building. Provide tracer wire for non-metallic water service pipe. [Initial comment: Show the location and size of the proposed water meter and the proposed size, material, and route of the water service pipe on a site plan. Provide tracer wire for non-metallic water service pipe. Reference: Section 107.2.1 and 107.2.6, IBC 2018.] | ||
| 10/03/2024 | Fire New Construction | REVIEW COMPLETED | |||
| 09/05/2024 | PDSD Application Completeness Express | REVIEW COMPLETED |