Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - LIMITED v.2
Permit Number - TC-COM-0724-01285
Review Name: COMMERCIAL REVIEW - LIMITED v.2
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/05/2024 | Commercial Plumbing | APPROVED | |||
07/30/2024 | Site Zoning | APPROVED | |||
08/02/2024 | Site Engineering | NOT REQUIRED | |||
08/05/2024 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
07/30/2024 | Commercial Electrical | REQUIRES RESUBMIT | Please address the electrical plan review comments and provide a written response. 1 The registrant seal is not sign and dated. Also the expiration date is missing. 2 Show the electric hot water heater location, disconnecting means and branch circuit on the power plan.. 3 Provide for GFI protection for receptacles within 6 ft of the sinks where applicable, Treatment rooms #4 and #5. Ref; 2018 IBC section 107.2.1, 2017 NEC |
||
08/02/2024 | Commercial Mechanical | REQUIRES RESUBMIT | 1. Show how the dryer exhaust duct is to be separated from the outside air intakes for the fan coil units. Reference: Section 501.3.1, IMC 2018. 2. Revise the mechanical design as required to avoid using the corridors as return air ducts. Reference: Section 601.2, IMC 2018. |
||
08/05/2024 | Commercial Structural | REQUIRES RESUBMIT | Please submit your revised documents and provide a letter with a written response letter to address each of the comments indicating how the Building Review comments were addressed. Additionally, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. 1. Sheet A2.0: Please amend plans to provide clear floor space, knee and toe space for forward approach for break room sink as described below. 2009 ICC A117.1 606.2 A. A clear floor space complying with Section 305.3, positioned for forward approach, shall be provided. Knee and toe clearance complying with Section 306 shall be provided. The dip of the overflow shall not be considered in determining knee and toe clearances. EXCEPTIONS: 1.A parallel approach complying with Section 305 and centered on the sink, shall be permitted to a kitchen sink in a space where a cook top or conventional range is not provided. 2. Sheet A6.0 detail 2: Please amend drawing to show the front of lavatories and sinks shall be 34 inches maximum above the floor, measured to the higher of the rim or counter surface. 2009 ICC A117.1 606.3 Please contact me if you have any questions about these comments. Mark Masek Plans Examiner – Building Safety Planning and Development Services | City of Tucson main 520.837.4994 email mark.masek@tucsonaz.gov |
||
08/01/2024 | Fire New Construction | REVIEW COMPLETED | |||
07/16/2024 | PDSD Application Completeness | REVIEW COMPLETED |