Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0723-01864
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/02/2023 | Site Zoning | APPROVED | |||
09/06/2023 | Water - PDSD | APPROVED | |||
08/02/2023 | Site Engineering | NOT REQUIRED | |||
09/06/2023 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
08/17/2023 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Structural(S) Reviewer Daljit Benipal dbenipal@safebuilt.com Denied Reason: Date Completed : 8/10/2023 12:34:44 PM 1. Refer to Structural Calculations submitted. Sheet C-32 shows member W14x34 failing in bending by 6.8% and have excessive deflections. Verify and submit response. 2. Refer to Structural Calculations submitted. Sheet C-35 shows member W14x34 failing in bending by 17.3% and have excessive deflections. Verify and submit response. 3. Refer to Structural Calculations submitted. Sheet C-38 shows member W14x34 failing in bending by 8.4% and have excessive deflections. Verify and submit response. 4. Refer to Structural Calculations submitted. Sheet C-41 shows member W14x34 failing in bending by 13.3% and have excessive deflections. Verify and submit response. 5. DEFERRED SUBMITTAL REQUIREMENTS Structural general notes are to include any components of the building that may be considered deferred submittals. IBC Section 107.3.4.1 requires deferred submittals to be approved by the building official. If items will be deferred the plans are to clearly note the following per IBC Section 107.3.4.1: * To be reviewed by design professional in responsible charge. * Design professional shall affix a notation that the deferred items are in general conformance with their design of the building. * They shall be submitted for review by the building official. * Shall not be installed until approved by building official. Submit a response letter addressing these correction items and provide bubbles on the revisions to the drawings. Building(B) Reviewer Andrew Bevis abevis@safebuilt.com Denied Reason: Date Completed : 8/4/2023 3:14:57 PM 1. Sheet G001: The base allowable area is incorrect. Since non-separated mix use is being used, the most restrictive base allowable area is required to be used. The A-3 use is the most restrictive. Provide a corrected allowable base area. 2. Sheet G003: Provide clarification as to why both the E and I-4 occupancy classification is being used? If the children are always going to be under 2.5 years of age classify it as an E. If the ages are going to be unknown and the amount of children fluctuate frequently, used the I-4 designation. 3. Sheet G003: Rooms that are designated at I-4 use are required to have not less than two exits. Provide additional exits in accordance with Section 1006.2.2.4. 4. General: Provide clarification on the uses of the adjacent tenant spaces to ensure proper tenant separation. 5. Sheet A102:8.Exercise equipment is required have clear floor space for access. Ensure clear floor space in accordance with Section 236.1 of the 2010 ADAAG. 6. Sheet A102: Provide section detail drawings of the exercise platforms. It appears that the ramps may not meet the maximum slope requirements for accessibility in accordance with Section 1012.2. 7. Sheet A102: It appears that the minimum aisle width have not been maintained between the back of the equipment and the next platform. Provide evidence of compliance in accordance with Section 1018. 8. All RCP: Indicate the location of all EXIT and EXIT directional signage within the Life Safety Plan. Coordinate these locations with the electrical designer. (2018 IBC Sec. 1008 and 1013) Mechanical(M) Reviewer Neil Samaan nsamaan@safebuilt.com Denied Reason: Date Completed : 8/6/2023 1:44:00 AM 1. Room# 104, 110,111,133,135 is above the refrigeration concentration limit (MMC2018,1104.4) 2. Provide ventilation calculations (MMC2018,403.3.1.1.1) 3. Smoke detectors shall be installed in return air systems with a design capacity greater than 2,000 cfm for VFC-1 & VFC-5 (MMC2018,606.2.1) 4. Duct smoke detectors shall be tied into the fire alarm system (MMC2018,606.4.1) Electrical(E) Reviewer Ron Ross rross@safebuilt.com Approved with Comments Reason: Date Completed : 8/10/2023 5:43:28 PM Electrical Review of Chuze Fitness By: Ron Ross PE Electrical approved with the following comments to correct or revise for construction set. E001 ELECTRICAL SITE PLAN: Not included in set, but E110 sheet seemed sufficient. E110 ELECTRICAL LIGHTING FLOOR PLAN: Could not locate Keynotes 2, 6, and 12. E120 ELECTRICAL ROOF POWER PLAN: Could not locate Keynote 3. E401 ENLARGED ELECTRICAL PLANS: Could not locate Keynotes 10, 11, 15, 17, 21, and 22. Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Denied Reason: Date Completed : 8/15/2023 10:17:12 PM First Plumbing Review: 1). Plan page P601 water heater schedule list a EWH-1 point of use EEmax water heater, there is not a EWH-1 shown on the water piping plan P401, and this doesn't correlate with the existing 1" hot water system shown supplying the hot piping in the remodeled areas. See P111 & P401. plan pages need to correlate -IPC 106.3.1 2). Lavs on P601 need ASSE 1070 mixing valves - IPC 419.5 3). P602 trap primer detail needs a shut off valve - IPC 606.2 |
||
08/13/2023 | Fire New Construction | REVIEW COMPLETED | |||
08/02/2023 | PDSD Application Completeness | REVIEW COMPLETED |