Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0723-01695
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
08/10/2023 Commercial Plumbing APPROVED
07/14/2023 Site Zoning APPROVED
07/18/2023 Site Engineering NOT REQUIRED
08/14/2023 Bldg Permits - Post Review PENDING ASSIGNMENT
08/08/2023 Commercial Electrical REQUIRES RESUBMIT Please address the electrical plan review comments and provide a written response.

1 Plan sheets ‘a1.10’, 11, 12, 20, and 21 RCP notes make reference to electrical power and lighting plans. Could not locate either in the submitted plan set. Please clarify.

Ref; 2018 IBC section 107.2.1, 2017 NEC, 2018 IECC.
08/10/2023 Commercial Mechanical REQUIRES RESUBMIT 1. As new work, the hoods for the ranges must either provide the minimum kitchen ventilation called for in Table 403.3.1.1, IMC 2018, or if the hoods are ductless, local exhaust shall be provided for the kitchen per Section 403.3.2.3, IMC 2018. Reference: Section 505.3, exception 1, IMC 2018.
2. Replacement of any AC equipment will require a heating/cooling load calculation to justify the capacities of the units being installed (Sections R403.7, IECC 2018). The units themselves will also have to comply with Sections R403.1 and R503.1.2, IECC 2018 for efficiency and controls.
08/14/2023 Commercial Structural REQUIRES RESUBMIT Submit your revised drawings along with a detailed response letter, which states how all Building Review Section comments were addressed.
1. IBC 1107 & Table 1107.6.1.1 Accessible units required, also comply to IEBC 305.8.6 accessible units requirement pointing to IBC 1107.
2. IBC 1106 & Table 1106.1 Accessible parking required, includes sign on post and striped accessible route.
3. Please re-submit
07/17/2023 Fire New Construction REVIEW COMPLETED
07/13/2023 PDSD Application Completeness REVIEW COMPLETED