Permit Number: TC-COM-0723-01651
Parcel: 10821328B

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0723-01651
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
07/11/2023 Site Zoning APPROVED
08/03/2023 Water - PDSD APPROVED
07/10/2023 Site Engineering NOT REQUIRED
08/03/2023 Bldg Permits - Post Review PENDING ASSIGNMENT
07/10/2023 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Activity Number: TC-COM-0723-01651

GENERAL:
Provide written responses to all review comments.
Provide a complete plan set.
Provide additional documents as requested by review staff.


Structural(S) Reviewer
Kimiyoshi Shimabukuro
kshimabukuro@safebuilt.com
Denied
Reason:
Date Completed : 7/8/2023 11:35:06 PM
1. Designer of record stamp expired in 09.30.22.


Building(B) Reviewer
Kimiyoshi Shimabukuro
kshimabukuro@safebuilt.com
Denied
Reason:
Date Completed : 7/8/2023 11:35:19 PM
1. Designer of record stamp expired in 09.30.22.
2. Sheet A1.0 – Plumbing fixture calculations show to provide at common area restroom but this is not shown in plan.
How far is the common area restrooms? Does it combine with entire building occupants or separate for this suite 110 only?
3. Sheet A1.1 – What are the materials stored in open storage area? Does it contain hazardous materials identified in 2018 IBC section 414?
4. Sheet A1.1 – Maximum common path of egress set at 100’ but actual common path of egress is not provided from team office 111.


Mechanical(M) Reviewer
Kimiyoshi Shimabukuro
kshimabukuro@safebuilt.com
Denied
Reason:
Date Completed : 7/8/2023 11:36:57 PM
1. Designer of record stamp expired in 09.30.22.
2. Sheet M2.0 – How and to what is the fan coil unit Unistrut in 103/M2.0 connected?
3. Provide energy code calculations (COMcheck) according to 2018 IECC.


Electrical(E) Reviewer
Kimiyoshi Shimabukuro
kshimabukuro@safebuilt.com
Denied
Reason:
Date Completed : 7/8/2023 11:40:09 PM
1. Designer of record stamp expired in 09.30.22.
2. Sheet E1.0 – Single line diagram and panel schedules missing. One line diagram include panel numbers, voltage, phasing, location, bus size, circuit number, breaker sizing, number of poles, A.I.C rating number of lights and/or receptacles by circuit, total KVA load.
3. Sheet E2.0 – New fan coil units powers missing


Plumbing(P) Reviewer
Kimiyoshi Shimabukuro
kshimabukuro@safebuilt.com
Denied
Reason:
Date Completed : 7/8/2023 11:36:32 PM
1. Designer of record stamp expired in 09.30.22.
2. Sheet A1.0 – Plumbing fixture calculations show to provide at common area restroom but this is not shown in plan.
How far is the common area restrooms? Does it combine with entire building occupants or separate for this suite 110 only?
3. Sheet P1.0/P2.0 – How and to what is the sub-out in wet column connected? New condensate drains now shown in P2.0.
07/26/2023 Fire New Construction REVIEW COMPLETED
07/07/2023 PDSD Application Completeness REVIEW COMPLETED