Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0723-01638
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/03/2023 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
07/26/2023 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Structural(S) Reviewer Daljit Benipal dbenipal@safebuilt.com Denied Reason: Date Completed : 7/25/2023 4:27:37 PM 1. Provide accurate information regarding Current Codes per International Building Code 2018. The information provided is incorrect since State has adopted latest Codes. The Enercalc Calculations submitted page marked H5 calls for IBC2012 and ASCE7-10. Make revisions as needed. 2. Provide accurate information regarding Current Codes per International Building Code 2018. The information provided is incorrect since State has adopted latest Codes. The Enercalc Calculations submitted page marked H9 calls for IBC2012 and ASCE7-10. Make revisions as needed. 3. Provide accurate information regarding Current Codes per International Building Code 2018. The information provided is incorrect since State has adopted latest Codes. The Enercalc Calculations submitted page marked H16 calls for IBC2012 and ASCE7-10. Make revisions as needed. 4. Provide accurate information regarding Current Codes per International Building Code 2018. The information provided is incorrect since State has adopted latest Codes. The Enercalc Calculations submitted page marked H21 calls for IBC2012 and ASCE7-10. Make revisions as needed. 5. Provide accurate information regarding Current Codes per International Building Code 2018. The information provided is incorrect since State has adopted latest Codes. The Enercalc Calculations submitted page marked H27 calls for IBC2012 and ASCE7-10. Make revisions as needed. 6. Provide accurate information regarding Current Codes per International Building Code 2018. The information provided is incorrect since State has adopted latest Codes. The Enercalc Calculations submitted page marked H31 calls for IBC2012 and ASCE7-10. Make revisions as needed. 7. Provide accurate information regarding Current Codes per International Building Code 2018. The information provided is incorrect since State has adopted latest Codes. The Enercalc Calculations submitted page marked H38 calls for IBC2012 and ASCE7-10. Make revisions as needed. 8. Provide accurate information regarding Current Codes per International Building Code 2018. The information provided is incorrect since State has adopted latest Codes. The Enercalc Calculations submitted page marked H60 calls for IBC2012 and ASCE7-10. Make revisions as needed. 9. Provide accurate information regarding Current Codes per International Building Code 2018. The information provided is incorrect since State has adopted latest Codes. The Enercalc Calculations submitted page marked H67 calls for IBC2012 and ASCE7-10. Make revisions as needed. 10. Provide accurate information regarding Current Codes per International Building Code 2018. The information provided is incorrect since State has adopted latest Codes. The Enercalc Calculations submitted page marked H102 calls for IBC2012 and ASCE7-10. Make revisions as needed. 11. Provide accurate information regarding Current Codes per International Building Code 2018. The information provided is incorrect since State has adopted latest Codes. The Enercalc Calculations submitted page marked H108 calls for IBC2012 and ASCE7-10. Make revisions as needed. 12. Provide accurate information regarding Current Codes per International Building Code 2018. The information provided is incorrect since State has adopted latest Codes. The Enercalc Calculations submitted page marked H117 calls for IBC2012 and ASCE7-10. Make revisions as needed. 13. Submit documentation regarding implementation of Special Inspections and Testing program during construction to observe compliance with the Design Concepts and Specifications. 14. Provide schedule of special inspections as required in IBC Section 1705. 15. DEFERRED SUBMITTAL REQUIREMENTS Structural general notes are to include any components of the building that may be considered deferred submittals. IBC Section 107.3.4.1 requires deferred submittals to be approved by the building official. If items will be deferred the plans are to clearly note the following per IBC Section 107.3.4.1: * To be reviewed by design professional in responsible charge. * Design professional shall affix a notation that the deferred items are in general conformance with their design of the building. * They shall be submitted for review by the building official. * Shall not be installed until approved by building official. Submit a response letter addressing these correction items and provide bubbles on the revisions to the drawings. Building(B) Reviewer Andrew Bevis abevis@safebuilt.com Denied Reason: Date Completed : 7/14/2023 12:27:00 PM 1. Sheet G02: The project code summary table states the business use and factory use are indicated as accessory occupancies. However, the areas of these areas individually exceed the maximum allowable areas for accessory occupancies (10% of the floor) and exceed the tabular values for non-sprinklered buildings in accordance with Section 508.2.3. The aggregate areas of these areas cannot exceed these values. Provide accessory areas that are in compliance with Section 508.2.3. 2. General: Provide clarification on the painting methods/processes provided in the shop area. If "doping" is occurring additional requirements apply. Provide clarification in relation to Section 412.3.5. Mechanical(M) Reviewer Neil Samaan nsamaan@safebuilt.com Denied Reason: Date Completed : 7/7/2023 8:37:10 PM 1. The process of “doping,” involving use of a volatile flammable solvent, or of painting, shall be carried on in a separate detached building equipped with automatic fire-extinguishing equipment in accordance with Section 903. (IBC2018,412.4.5) sheet m200 2. Smoke detectors shall be installed in return air systems with a design capacity greater than 2,000 cfm for on sheet M200 (IMC2018,606.2.1) Electrical(E) Reviewer Ron Ross rross@safebuilt.com Denied Reason: Date Completed : 7/18/2023 9:01:11 AM Electrical Review of SkyWest By: Ron Ross PE E1.00 ELECTRICAL SITE PLAN: Keynote 6 and picture do not agree. Picture does not show 100-amp receptacle. Other notes (16 & 17) correctly reference this picture. Suggest to add another picture showing correct plug or revise note. E2.00 LIGHTING PLAN - AREA A: Missing Keynote 15. E2.03 LIGHTING PLAN - AREA D: Keynote 8 should be removed/replaced from Hanger area or modified on this sheet. E2.06 POWER PLAN - AREA C: Missing Keynote #6. E2.08 HVAC POWER PLAN - AREA A: Could not locate Keynotes 6, 8, 9, and 10 on any of the following sheets E2.08- E2.11. E2.13 SPECIAL SYSTEMS PLAN - AREA B: Could not locate Keynote #2. E2.15 SPECIAL SYSTEMS PLAN - AREA D: Could not locate Keynote #2. E3.00 ONE LINE DIAGRAM & DETAILS: Generator needs to have a neutral to provide voltage stabilization especially for any 277V circuits. No neutral is provided. May need to also provide a 4 pole ATS for application. Panel L3 sect 1 has undersized 225 A MCB rating for a 150 KVA transformer. E3.01 PANEL SCHEDULES: Panel L3 sect 1 has undersized 225 A MCB rating for a 150 KVA transformer. Panel L3 sect 2 has undersized 225 A MLO rating. Panel L5 needs an MCB and has two different ampacity ratings. Correct. Panel L6 has a 225 Amp MCB vs one-line calls for it to have a 400-amp MCB to match 150 KVA transformer. Coordinate. Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Denied Reason: Date Completed : 7/19/2023 9:27:53 PM First Plumbing Review: 1). The 2.5" gas line piping configuration at the building entrance on plan page P-001 doesn't correlate with plan page P-101. Plan page P-001 doesn't show an incoming line to the meter and shows a 2.5" line being piped off in an unknown direction. pages to need to correlate. -IFGC 106.3.1 2). The #5 sediment trap detail on plan page P401 needs to match # 6 detail on the same page, the sediment trap can't be installed on the horizontal run. -IFGC 408.4 3). Dump station water supply Detail #3 on P401 needs to show a high hazard RPZ backflow for this application. -IPC table 608.1 4). Add gutter & downspout sizing calculations to plan page A22 -IPC 1106.1, 1106.3, 1106.6 5). Show gutter & downspout locations & sizes on Plan page A22 -IPC 1106.3, 1106.6 6). Lavatories need ASSE 1070 mixing valves update plan page P-001 or sheet 224000-8 of spec manual -IPC 419.5 7). Spec manual or plumbing plans need to in gas piping, fittings, & hanger information. - IFGC 403 8). Compressor C1 & C2 locations not clear on plan page P101 -IPC 106.3.1 9). Add compressor detail to plan page P401 -IPC 106.3.1 |
||
07/18/2023 | Site Engineering | REQUIRES RESUBMIT | 1. See Zoning Comment 2. Ensure roof drainage matches that shown on the development package Scott Haseman scott.haseman@tucsonaz.gov |
||
07/13/2023 | Site Zoning | REQUIRES RESUBMIT | FROM: Paul Camarena PDSD Zoning Review Section PROJECT: TC-COM-0723-01638 7250 S TUCSON BL Zoning MU TRANSMITTAL DATE:July 13, 2023 COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1.COMMENT: Zoning has reviewed the building plan for compliance with the unapproved DP22-0134 and although it appears that the building plans match the DP Zoning cannot approve the building plans until the DP is approved. 2. COMMENT: Zoning will review the building plans on the next submittal as it relates to the zoning review purview and compare the building plan footprint, building height, and square footage and location to ensure consistency with the DP. Please remove the unapproved DP plans from the plan set. If you have any questions about this transmittal, Contact Paul Camarena at (520)837-4986 or by email Paul.Camarena@tucsonaz.gov |
||
08/03/2023 | Water - PDSD | REQUIRES RESUBMIT | An approved development plan is not to be used for construction of on-site utilities (e.g. water service to the building, building sewer, etc.). Provide a site drawing showing the size and route of the building water supply along with the location and size of both the water meter and the reduced pressure backflow preventer assembly. Reference: Section 107.2.1, IBC 2018. | ||
07/31/2023 | Fire New Construction | REVIEW COMPLETED | |||
07/06/2023 | PDSD Application Completeness | REVIEW COMPLETED |